Connect to Innovate Program – Project status updates

This page provides information about the status of Connect to Innovate (CTI) high-speed Internet projects in each community where they will be providing service.

The following table displays the status of announced CTI projects with finalized contribution agreements. Announced projects not listed in this table are still under negotiation and will be added once the details of their agreements have been finalized. Updates to this table will occur on a quarterly basis in March, June, September, and December.

While the CTI program was originally set to close in March 2023, the completion deadline for a select number of projects has been extended, as they experience delays due to the impact of COVID-19-related supply chain disruptions, labour shortages, and inflation. Once all projects are completed, CTI will bring new or improved high-speed Internet access to 975 rural and remote communities – more than triple the 300 communities initially targeted.

Communities connected by 2023
Communities connected by 2023
Results to date
December 2021 733
March 2022 766
June 2022 896
September 2022 913
December 2022 928
March 2023+ 1,079
Targets
December 2020 100
December 2021 750
March 2023 975
Households impacted by 2023
Households impacted by 2023
Results to date
December 2021 185,803
March 2022 199,156
June 2022 220,446
September 2022 226,177
December 2022 228,723
March 2023+ 285,652
Targets
December 2020 35,000
December 2021 250,000
March 2023 390,000
Status and number of contribution agreements
Status and number of contribution agreements
Status Number
Detailed design & construction stage 15
Operational stage 83
Total 98

975+
communities to be connected

190
Indigenous communities to be connected

390,000
households in communities with improved connectivity

1200
anchor institutions with improved connectivity

22,500km
of fibre will be installed

$585M
Total Connect to Innovate funding

 

You can search for projects in your province or by project status by entering it into the filter field below.

Reflects progress up to November 2024.

Filter Options

Province or territory CommunitiesFootnote 1 Project Name Footnote 2 Project DescriptionFootnote 3 Total CTI Funding
Footnote 4
Project Start DateFootnote 5 Current StageFootnote 6 Expected construction completion dateFootnote 7
Alberta Abee Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Atmore Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Beaver Lake Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Bellis Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Bigstone Cree (Jean Baptiste Gambler No.183) Arrow Technology Group GP Limited Backbone network using fibre optic technology to enhance broadband capacity to 8 communities in Northern Alberta. $6,040,533 2021-04-01 Operational 2022-03-31
Alberta Bigstone Cree (Wabasca No.166) Arrow Technology Group GP Limited Backbone network using fibre optic technology to enhance broadband capacity to 8 communities in Northern Alberta. $6,040,533 2021-04-01 Operational 2022-03-31
Alberta Bigstone Cree (Wabasca No.166B) Arrow Technology Group GP Limited Backbone network using fibre optic technology to enhance broadband capacity to 8 communities in Northern Alberta. $6,040,533 2021-04-01 Operational 2022-03-31
Alberta Bigstone Cree (Wabasca No.166C) Arrow Technology Group GP Limited Backbone network using fibre optic technology to enhance broadband capacity to 8 communities in Northern Alberta. $6,040,533 2021-04-01 Operational 2022-03-31
Alberta Bigstone Cree (Wabasca No.166D) Arrow Technology Group GP Limited Backbone network using fibre optic technology to enhance broadband capacity to 8 communities in Northern Alberta. $6,040,533 2021-04-01 Operational 2022-03-31
Alberta Bigstone Cree Nation Arrow Technology Group GP Limited Backbone network using fibre optic technology to enhance broadband capacity to 8 communities in Northern Alberta. $6,040,533 2021-04-01 Operational 2022-03-31
Alberta Birchcliff Missing Link Internet Inc Backbone network using fibre optic technology to enhance broadband capacity to 6 communities in the region of Sylvan Lake, AB. $1,326,882 2018-10-01 Operational 2020-08-30
Alberta Blackfoot Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Bondiss Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Campsie Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Carcajou Arrow Technology Group LP Limited Backbone network using fibre optic technology to enhance broadband capacity to 2 communities as well as a Last-Mile network using wireless technology to 3 additional communities to reach underserved households in the regions of Northern Lights and MacKenzie County, AB. $2,031,671 2018-09-01 Operational 2020-03-31
Alberta Cherry Grove Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Colinton Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Collingwood Cove Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Coronado Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Eagles Quay Missing Link Internet Inc Backbone network using fibre optic technology to enhance broadband capacity to 6 communities in the region of Sylvan Lake, AB. $1,326,882 2018-10-01 Operational 2020-08-30
Alberta Egremont Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Elmworth GPN Wireless Network Solutions Ltd (GPNetworks) Backbone network using fibre optic technology to enhance broadband capacity to 1 community in the Grand Prairie Region of Alberta. $802,553 2021-04-19 Operational 2022-08-30
Alberta Ferrier Acres Trailer Court Clearwater County Backbone network using fibre optic technology to enhance broadband capacity to 2 communities in the Central Region of Alberta. $371,288 2020-06-01 Operational 2022-03-31
Alberta Fort Chipewyan Arrow Technology Group GP Limited Backbone network using microwave technology to enhance broadband capacity to 2 communities in the region of Fort Chipewyan, Alberta. $768,150 2019-05-01 Operational 2020-03-31
Alberta Fort Kent Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Fox Lake (Little Red River Cree Nation) Arrow Technology Group LP Limited Backbone network using fibre optic technology to enhance broadband capacity to 3 communities in the regions of the MacKenzie County and Wood Buffalo, AB. $4,245,426 2018-09-01 Operational 2020-05-29
Alberta Garden Creek Arrow Technology Group LP Limited Backbone network using fibre optic technology to enhance broadband capacity to 3 communities in the regions of the MacKenzie County and Wood Buffalo, AB. $4,245,426 2018-09-01 Operational 2020-05-29
Alberta Gift Lake Arrow Technology Group LP Limited Backbone network using fibre optic technology to enhance broadband capacity to 2 communities as well as a Last-Mile network using wireless technology to 3 additional communities to reach underserved households in the regions of Northern Lights and MacKenzie County, AB. $2,031,671 2018-09-01 Operational 2020-03-31
Alberta Half Moon Bay Missing Link Internet Inc Backbone network using fibre optic technology to enhance broadband capacity to 6 communities in the region of Sylvan Lake, AB. $1,326,882 2018-10-01 Operational 2020-08-30
Alberta Half Moon Estates Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Hilliard Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Jarvis Bay Missing Link Internet Inc Backbone network using fibre optic technology to enhance broadband capacity to 6 communities in the region of Sylvan Lake, AB. $1,326,882 2018-10-01 Operational 2020-08-30
Alberta John D'Or Prairie Arrow Technology Group LP Limited Backbone network using fibre optic technology to enhance broadband capacity to 3 communities in the regions of the MacKenzie County and Wood Buffalo, AB. $4,245,426 2018-09-01 Operational 2020-05-29
Alberta Keg River Arrow Technology Group LP Limited Backbone network using fibre optic technology to enhance broadband capacity to 2 communities as well as a Last-Mile network using wireless technology to 3 additional communities to reach underserved households in the regions of Northern Lights and MacKenzie County, AB. $2,031,671 2018-09-01 Operational 2020-03-31
Alberta Keg River Arrow Technology Group LP Limited Backbone network using fibre optic technology to enhance broadband capacity to 2 communities as well as a Last-Mile network using wireless technology to 3 additional communities to reach underserved households in the regions of Northern Lights and MacKenzie County, AB. $2,031,671 2018-09-01 Operational 2020-03-31
Alberta La Glace GPNetworks Backbone network using fibre optic technology to enhance broadband capacity to 2 communities in northwestern Alberta. $986,657 2019-09-30 Operational 2020-03-31
Alberta Larkspur Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Leavitt Cardston County Backbone network using fibre optic technology to enhance broadband capacity to 1 community of Cardston County in the Mountain View Region of Southwest Alberta. $211,775 2019-01-21 Operational 2020-03-31
Alberta Martins Trailer Court Clearwater County Backbone network using fibre optic technology to enhance broadband capacity to 2 communities in the Central Region of Alberta. $371,288 2020-06-01 Operational 2022-03-31
Alberta Mewatha Beach Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Mikisew Cree Arrow Technology Group GP Limited Backbone network using microwave technology to enhance broadband capacity to 2 communities in the region of Fort Chipewyan, Alberta. $768,150 2019-05-01 Operational 2020-03-31
Alberta Norglenwold Missing Link Internet Inc Backbone network using fibre optic technology to enhance broadband capacity to 6 communities in the region of Sylvan Lake, AB. $1,326,882 2018-10-01 Operational 2020-08-30
Alberta O'Chiese Arrow Technology Group LP Limited Backbone network using fibre optic technology to enhance broadband capacity to 3 communities in the regions of Clearwater and Big Lakes, Alberta. $2,369,186 2020-04-01 Operational 2021-03-31
Alberta Peavine Metis Settlement Arrow Technology Group LP Limited Backbone network using fibre optic technology to enhance broadband capacity to 3 communities in the regions of Clearwater and Big Lakes, Alberta. $2,369,186 2020-04-01 Operational 2021-03-31
Alberta Pelican Narrows Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Pibroch Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Pickardville Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Rossian Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Salt Prairie Arrow Technology Group LP Limited Backbone network using fibre optic technology to enhance broadband capacity to 2 communities as well as a Last-Mile network using wireless technology to 3 additional communities to reach underserved households in the regions of Northern Lights and MacKenzie County, AB. $2,031,671 2018-09-01 Operational 2020-03-31
Alberta Sandy Lake Arrow Technology Group GP Limited Backbone network using fibre optic technology to enhance broadband capacity to 8 communities in Northern Alberta. $6,040,533 2021-04-01 Operational 2022-03-31
Alberta Spedden Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Sunbreaker Cove Missing Link Internet Inc Backbone network using fibre optic technology to enhance broadband capacity to 6 communities in the region of Sylvan Lake, AB. $1,326,882 2018-10-01 Operational 2020-08-30
Alberta Sunchild First Nation Arrow Technology Group LP Limited Backbone network using fibre optic technology to enhance broadband capacity to 3 communities in the regions of Clearwater and Big Lakes, Alberta. $2,369,186 2020-04-01 Operational 2021-03-31
Alberta Tallcree Arrow Technology Group LP Limited Backbone network using fibre optic technology to enhance broadband capacity to 2 communities as well as a Last-Mile network using wireless technology to 3 additional communities to reach underserved households in the regions of Northern Lights and MacKenzie County, AB. $2,031,671 2018-09-01 Operational 2020-03-31
Alberta Tallcree (Tallcree Tribal Government) Arrow Technology Group LP Limited Backbone network using fibre optic technology to enhance broadband capacity to 2 communities as well as a Last-Mile network using wireless technology to 3 additional communities to reach underserved households in the regions of Northern Lights and MacKenzie County, AB. $2,031,671 2018-09-01 Operational 2020-03-31
Alberta Therien Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Valhalla Centre GPNetworks Backbone network using fibre optic technology to enhance broadband capacity to 2 communities in northwestern Alberta. $986,657 2019-09-30 Operational 2020-03-31
Alberta Venice Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Warspite Buried Glass Inc. Backbone network using fibre optic technology to enhance broadband capacity to 23 communities using fibre optic technology to reach underserved households in the East Central and North Eastern regions in the province of Alberta. $7,336,912 2018-06-01 Operational 2021-03-31
Alberta Zama City Arrow Technology Group GP Limited Backbone network using fibre optic technology to enhance broadband capacity to 8 communities in Northern Alberta. $6,040,533 2021-04-01 Operational 2022-03-31
British Columbia 40 Mile Flats Tahltan Nation Development Corporation or TNDC Backbone network using fibre optic technology to enhance broadband capacity to 12 communities in northern British Columbia. $9,623,143 2019-06-25 Operational 2024-03-31
British Columbia Arras Shaw Cablesystems G.P. Backbone network using fibre optic technology to enhance broadband capacity to 10 communities in the region of Prince George to Dawson Creek, British Columbia. $9,317,532 2018-11-01 Operational 2023-08-31
British Columbia Barney's Bar City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Beecher Bay City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Bell II Tahltan Nation Development Corporation or TNDC Backbone network using fibre optic technology to enhance broadband capacity to 12 communities in northern British Columbia. $9,623,143 2019-06-25 Operational 2024-03-31
British Columbia Bella Bella (Heiltsuk) City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Operational 2025-03-31
British Columbia Bella Coola City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Blind Channel City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Bliss Landing City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Bob Quinn Lake Tahltan Nation Development Corporation or TNDC Backbone network using fibre optic technology to enhance broadband capacity to 12 communities in northern British Columbia. $9,623,143 2019-06-25 Operational 2024-03-31
British Columbia Bold Point City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Boothroyd Lyttonnet Backbone network using fibre optic technology to enhance broadband capacity to 4 communities in the Squamish-Lillooet region of British Columbia. $4,231,440 2020-07-01 Detailed Design & Construction 2025-03-31
British Columbia Bridge River Lyttonnet Backbone network using fibre optic technology to enhance broadband capacity to 4 communities in the Squamish-Lillooet region of British Columbia. $4,231,440 2020-07-01 Planning 2025-03-31
British Columbia Bull Harbour (Tlatlasikwala) City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Ceepeecee City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Chehalis (Sts'ailes) Sts'ailes Backbone network using fibre optic technology to enhance broadband capacity to 1 community in the region of Fraser Valley, BC. $132,030 2018-09-15 Operational 2019-05-31
British Columbia Coal Harbour City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Cranberry Junction Tahltan Nation Development Corporation or TNDC Backbone network using fibre optic technology to enhance broadband capacity to 12 communities in northern British Columbia. $9,623,143 2019-06-25 Operational 2024-03-31
British Columbia Da'naxda'xw First Nation City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Dease Lake Tahltan Nation Development Corporation or TNDC Backbone network using fibre optic technology to enhance broadband capacity to 12 communities in northern British Columbia. $9,623,143 2019-06-25 Operational 2024-03-31
British Columbia Ditidaht City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Operational 2025-03-31
British Columbia Dodge Cove City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Planning 2025-03-31
British Columbia Dokie Siding Shaw Cablesystems G.P. Backbone network using fibre optic technology to enhance broadband capacity to 10 communities in the region of Prince George to Dawson Creek, British Columbia. $9,317,532 2018-11-01 Operational 2023-08-31
British Columbia Earls Cove City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Operational 2025-03-31
British Columbia Echo Bay City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Egmont City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Ehatis 11 (Ehattesaht) City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Ehattesaht City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Elk Bay City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Esperanza City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Gillies Bay City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Gitanyow Tahltan Nation Development Corporation or TNDC Backbone network using fibre optic technology to enhance broadband capacity to 12 communities in northern British Columbia. $9,623,143 2019-06-25 Operational 2024-03-31
British Columbia Gold River City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Granite Bay City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Gwawaenuk Tribe City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Hartley Bay (Gitga'at First Nation) City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Hasler Flat Shaw Cablesystems G.P. Backbone network using fibre optic technology to enhance broadband capacity to 10 communities in the region of Prince George to Dawson Creek, British Columbia. $9,317,532 2018-11-01 Operational 2023-08-31
British Columbia Health Bay (Kwikwasut'inuxw Haxwa'mis) City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Operational 2025-03-31
British Columbia Hesquiaht City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Hesquiat City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Holberg City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Huu-ay-aht City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Huu-ay-aht First Nations City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Hyde Creek City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Iskut Tahltan Nation Development Corporation or TNDC Backbone network using fibre optic technology to enhance broadband capacity to 12 communities in northern British Columbia. $9,623,143 2019-06-25 Operational 2024-03-31
British Columbia Kingcome (Dzawada'enuxw First Nation) City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Kitkatla (Gitxaala Nation) City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Klahoose First Nation City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Klemtu (Kitasoo) City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Operational 2025-03-31
British Columbia Kwakiutl City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Kyuquot (Ka:'yu:'k't'h'/Che:k:tles7et'h' First Nations) City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Operational 2025-03-31
British Columbia Lasqueti City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Lawnhill Gwaii Communications Backbone network using fibre optic technology to enhance broadband capacity to 7 communities as well as a last-mile network using fibre optic technology to reach underserved households in the region of Haida Gwaii, British Columbia. $3,880,386 2018-08-01 Operational 2024-03-30
British Columbia Lax Kw'alaams City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Lemoray Shaw Cablesystems G.P. Backbone network using fibre optic technology to enhance broadband capacity to 10 communities in the region of Prince George to Dawson Creek, British Columbia. $9,317,532 2018-11-01 Operational 2023-08-31
British Columbia Lower Hat Creek 2 (Bonaparte) Shaw Cablesystems G.P. Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the region of Whistler to Cache Creek, British Columbia. $2,011,964 2018-09-01 Operational 2023-12-31
British Columbia Lyackson City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Mahatta River City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Operational 2025-03-31
British Columbia Mamalilikulla-Qwe'Qwa'Sot'Em (Mamalilikulla First Nation) City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Martin Valley City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia McLeod Lake Shaw Cablesystems G.P. Backbone network using fibre optic technology to enhance broadband capacity to 10 communities in the region of Prince George to Dawson Creek, British Columbia. $9,317,532 2018-11-01 Operational 2023-08-31
British Columbia Meziadin Junction Tahltan Nation Development Corporation or TNDC Backbone network using fibre optic technology to enhance broadband capacity to 12 communities in northern British Columbia. $9,623,143 2019-06-25 Operational 2024-03-31
British Columbia Miller Creek Gwaii Communications Backbone network using fibre optic technology to enhance broadband capacity to 7 communities as well as a last-mile network using fibre optic technology to reach underserved households in the region of Haida Gwaii, British Columbia. $3,880,386 2018-08-01 Operational 2024-03-30
British Columbia Mitchell Bay City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Mount Currie Shaw Cablesystems G.P. Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the region of Whistler to Cache Creek, British Columbia. $2,011,964 2018-09-01 Operational 2023-12-31
British Columbia Mowachaht/Muchalaht City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Musgrave Landing City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Myrtle Point City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Nass Camp Tahltan Nation Development Corporation or TNDC Backbone network using fibre optic technology to enhance broadband capacity to 12 communities in northern British Columbia. $9,623,143 2019-06-25 Operational 2024-03-31
British Columbia Nenagwas (Tlowitsis Nation) City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia New Aiyansh (Nisga'a Village of New Aiyansh) Tahltan Nation Development Corporation or TNDC Backbone network using fibre optic technology to enhance broadband capacity to 12 communities in northern British Columbia. $9,623,143 2019-06-25 Operational 2024-03-31
British Columbia New Brighton City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Nuchatlaht City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Ocean Falls City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Oona River City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Open Bay City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Operational 2025-03-31
British Columbia Opitsat (Tla-o-qui-aht First Nations) City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Oweekeno (Wuikinuxv Nation) City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Pacheedaht First Nation City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Pavilion (Ts'kw'aylaxw First Nation) Shaw Cablesystems G.P. Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the region of Whistler to Cache Creek, British Columbia. $2,011,964 2018-09-01 Operational 2023-12-31
British Columbia Penelakut (Penelakut Tribe) City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Pine Valley Shaw Cablesystems G.P. Backbone network using fibre optic technology to enhance broadband capacity to 10 communities in the region of Prince George to Dawson Creek, British Columbia. $9,317,532 2018-11-01 Operational 2023-08-31
British Columbia Port Clements Gwaii Communications Backbone network using fibre optic technology to enhance broadband capacity to 7 communities as well as a last-mile network using fibre optic technology to reach underserved households in the region of Haida Gwaii, British Columbia. $3,880,386 2018-08-01 Operational 2024-03-30
British Columbia Port Neville City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Progress Shaw Cablesystems G.P. Backbone network using fibre optic technology to enhance broadband capacity to 10 communities in the region of Prince George to Dawson Creek, British Columbia. $9,317,532 2018-11-01 Operational 2023-08-31
British Columbia Quatsino City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Quatsino First Nation City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Read Island City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Refuge Cove City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia River Jordan City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Rock Bay City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Rumble Beach City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Salmon Valley Shaw Cablesystems G.P. Backbone network using fibre optic technology to enhance broadband capacity to 10 communities in the region of Prince George to Dawson Creek, British Columbia. $9,317,532 2018-11-01 Operational 2023-08-31
British Columbia Saltery Bay City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Sandspit Gwaii Communications Backbone network using fibre optic technology to enhance broadband capacity to 7 communities as well as a last-mile network using fibre optic technology to reach underserved households in the region of Haida Gwaii, British Columbia. $3,880,386 2018-08-01 Operational 2024-03-30
British Columbia Saturna City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Seaford City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Shawl Bay City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Shearwater City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Skidegate Landing Gwaii Communications Backbone network using fibre optic technology to enhance broadband capacity to 7 communities as well as a last-mile network using fibre optic technology to reach underserved households in the region of Haida Gwaii, British Columbia. $3,880,386 2018-08-01 Operational 2024-03-30
British Columbia Skuppah Lyttonnet Backbone network using fibre optic technology to enhance broadband capacity to 4 communities in the Squamish-Lillooet region of British Columbia. $4,231,440 2020-07-01 Detailed Design & Construction 2025-03-31
British Columbia Sliammon (Tla'amin Nation) City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Sointula City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Summit Lake Shaw Cablesystems G.P. Backbone network using fibre optic technology to enhance broadband capacity to 10 communities in the region of Prince George to Dawson Creek, British Columbia. $9,317,532 2018-11-01 Operational 2023-08-31
British Columbia Surge Narrows City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Tahltan Tahltan Nation Development Corporation or TNDC Backbone network using fibre optic technology to enhance broadband capacity to 12 communities in northern British Columbia. $9,623,143 2019-06-25 Operational 2024-03-31
British Columbia Tahsis City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Tatogga Tahltan Nation Development Corporation or TNDC Backbone network using fibre optic technology to enhance broadband capacity to 12 communities in northern British Columbia. $9,623,143 2019-06-25 Operational 2024-03-31
British Columbia Telegraph Cove City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia T'it'q'et Lyttonnet Backbone network using fibre optic technology to enhance broadband capacity to 4 communities in the Squamish-Lillooet region of British Columbia. $4,231,440 2020-07-01 Planning 2025-03-31
British Columbia Tla-o-qui-aht City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Tlell City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Operational 2025-03-31
British Columbia Tlell Gwaii Communications Backbone network using fibre optic technology to enhance broadband capacity to 7 communities as well as a last-mile network using fibre optic technology to reach underserved households in the region of Haida Gwaii, British Columbia. $3,880,386 2018-08-01 Operational 2024-03-30
British Columbia Toquaht City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Tow Hill Gwaii Communications Backbone network using fibre optic technology to enhance broadband capacity to 7 communities as well as a last-mile network using fibre optic technology to reach underserved households in the region of Haida Gwaii, British Columbia. $3,880,386 2018-08-01 Operational 2024-03-30
British Columbia Ts'kw'aylaxw Shaw Cablesystems G.P. Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the region of Whistler to Cache Creek, British Columbia. $2,011,964 2018-09-01 Operational 2023-12-31
British Columbia Uchucklesaht City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Upper Hat Creek 1 (Bonaparte) Shaw Cablesystems G.P. Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the region of Whistler to Cache Creek, British Columbia. $2,011,964 2018-09-01 Operational 2023-12-31
British Columbia Van Anda City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Wabi Hill Shaw Cablesystems G.P. Backbone network using fibre optic technology to enhance broadband capacity to 10 communities in the region of Prince George to Dawson Creek, British Columbia. $9,317,532 2018-11-01 Operational 2023-08-31
British Columbia Whaletown City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Williams Beach City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Winter Harbour City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Xaxli'p Shaw Cablesystems G.P. Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the region of Whistler to Cache Creek, British Columbia. $2,011,964 2018-09-01 Operational 2023-12-31
British Columbia Yaculta City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
British Columbia Yuquot City West Cable & Telephone Corp. Backbone network using fibre optic technology to enhance broadband capacity to 89 communities in central and northern region of Vancouver Island, British Columbia. $16,933,612 2018-01-01 Detailed Design & Construction 2025-03-31
Manitoba Altamont RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Anama Bay (Dauphin River) Broadband Communications North Inc. (BCN) Backbone network using fibre optic technology to enhance broadband capacity to 6 communities as well as a Last-mile network usingto reach underserved housholds in Northern Manitoba. $1,116,031 2019-04-01 Operational 2025-03-31
Manitoba Aubigny Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 18 communities in the Pembina Valley region of South Central Manitoba. $6,930,080 2020-08-02 Operational 2022-06-30
Manitoba Austin RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Bagot RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Baldur RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Barren Lands (Brochet) Broadband Communications North inc. (BCN) Backbone network using satellite technology to enhance broadband capacity to 16 communities in the Northern region of Mantioba. $13,193,381 2019-08-01 Operational 2024-03-31
Manitoba Belmont RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Berens River Bell Canada Backbone network using microwave to enhance broadband capacity to 8 communities in the province of Manitoba. $2,598,705 2018-10-01 Operational 2021-06-30
Manitoba Berens River Broadband Communications North inc. (BCN) Backbone network using satellite technology to enhance broadband capacity to 16 communities in the Northern region of Mantioba. $13,193,381 2019-08-01 Operational 2024-03-31
Manitoba Birdtail Sioux RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Bloodvein Broadband Communications North inc. (BCN) Backbone network using satellite technology to enhance broadband capacity to 16 communities in the Northern region of Mantioba. $13,193,381 2019-08-01 Operational 2024-03-31
Manitoba Blumenfeld Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Blumenort South Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Bradwardine RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Bristol Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 18 communities in the Pembina Valley region of South Central Manitoba. $6,930,080 2020-08-02 Operational 2022-06-30
Manitoba Brokenhead Reserve (Brokenhead Ojibway Nation) High Speed Crow Backbone network using fibre optic technology to enhance broadband capacity to 2 communities in Manitoba. $793,905 2019-07-08 Operational 2023-03-31
Manitoba Brunkild Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 18 communities in the Pembina Valley region of South Central Manitoba. $6,930,080 2020-08-02 Operational 2022-06-30
Manitoba Carberry RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Cardinal RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Carman Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Chortitz Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Clanwilliam RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Cromer RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Cross Lake (Cross Lake Band of Indians) Kici Sipi Communications LP Backbone network using fibre optic technology to enhance broadband capacity to 2 communities in Northern Region of Manitoba. $19,967,992 2021-07-31 Detailed design & construction 2024-12-30
Manitoba Cypress River RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Dallas Bell Canada Backbone network using microwave to enhance broadband capacity to 8 communities in the province of Manitoba. $2,598,705 2018-10-01 Operational 2021-06-30
Manitoba Dunrea RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Easterville RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Ebb and Flow One Nation Networks (a division of WiBand Communications Corp.) Backbone network using fibre optic technology to enhance broadband capacity to the Ebb and Flow First Nation in Manitoba. $3,468,772 2020-06-01 Operational 2024-12-31
Manitoba Ebb and Flow First Nation Corridor Communications Inc. (Xplore Inc.) Backbone network using fibre optic technology to enhance broadband capacity to the Ebb and Flow First Nation in Manitoba. $561,277 2020-07-01 Detailed Design & Construction 2025-03-31
Manitoba Elm Creek RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Fisher Branch Bell Canada Backbone network using microwave to enhance broadband capacity to 8 communities in the province of Manitoba. $2,598,705 2018-10-01 Operational 2021-06-30
Manitoba Fisher River Bell Canada Backbone network using microwave to enhance broadband capacity to 8 communities in the province of Manitoba. $2,598,705 2018-10-01 Operational 2021-06-30
Manitoba Friedensfeld Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 18 communities in the Pembina Valley region of South Central Manitoba. $6,930,080 2020-08-02 Operational 2022-06-30
Manitoba Friedensfeld West Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Friedensruh Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Giroux Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 18 communities in the Pembina Valley region of South Central Manitoba. $6,930,080 2020-08-02 Operational 2022-06-30
Manitoba Gnadenfeld Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Gnadenthal Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba God's Lake First Nation Broadband Communications North inc. (BCN) Backbone network using satellite technology to enhance broadband capacity to 16 communities in the Northern region of Mantioba. $13,193,381 2019-08-01 Operational 2024-03-31
Manitoba Gods River (Manto Sipi Cree Nation) Broadband Communications North inc. (BCN) Backbone network using satellite technology to enhance broadband capacity to 16 communities in the Northern region of Mantioba. $13,193,381 2019-08-01 Operational 2024-03-31
Manitoba Grand Rapids Broadband Communications North Inc. (BCN) Backbone network using fibre optic technology to enhance broadband capacity to 6 communities as well as a Last-mile network usingto reach underserved housholds in Northern Manitoba. $1,116,031 2019-04-01 Operational 2025-03-31
Manitoba Grand Rapids (Misipawistik Cree Nation) Broadband Communications North Inc. (BCN) Backbone network using fibre optic technology to enhance broadband capacity to 6 communities as well as a Last-mile network usingto reach underserved housholds in Northern Manitoba. $1,116,031 2019-04-01 Operational 2025-03-31
Manitoba Greenland Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 18 communities in the Pembina Valley region of South Central Manitoba. $6,930,080 2020-08-02 Operational 2022-06-30
Manitoba Greenway RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Gretna Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Harding RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Haskett Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Haywood RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Hochfeld Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Holland RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Homewood Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 18 communities in the Pembina Valley region of South Central Manitoba. $6,930,080 2020-08-02 Operational 2022-06-30
Manitoba Horndean Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Jackhead (Kinonjeoshtegon First Nation) Bell Canada Backbone network using microwave to enhance broadband capacity to 8 communities in the province of Manitoba. $2,598,705 2018-10-01 Operational 2021-06-30
Manitoba Kenton RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Killarney South RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba La Salle Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 18 communities in the Pembina Valley region of South Central Manitoba. $6,930,080 2020-08-02 Operational 2022-06-30
Manitoba Lac Brochet (Northlands Denesuline First Nation) Broadband Communications North inc. (BCN) Backbone network using satellite technology to enhance broadband capacity to 16 communities in the Northern region of Mantioba. $13,193,381 2019-08-01 Operational 2024-03-31
Manitoba Lake St. Martin Broadband Communications North Inc. (BCN) Backbone network using fibre optic technology to enhance broadband capacity to 6 communities as well as a Last-mile network usingto reach underserved housholds in Northern Manitoba. $1,116,031 2019-04-01 Operational 2025-03-31
Manitoba Linden Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 18 communities in the Pembina Valley region of South Central Manitoba. $6,930,080 2020-08-02 Operational 2022-06-30
Manitoba Little Black River (Black River First Nation) Broadband Communications North Inc. (BCN) Backbone network using fibre optic technology to enhance broadband capacity to 6 communities as well as a Last-mile network usingto reach underserved housholds in Northern Manitoba. $1,116,031 2019-04-01 Detailed Design & Construction 2025-03-31
Manitoba Little Grand Rapids Bell Canada Backbone network using microwave to enhance broadband capacity to 8 communities in the province of Manitoba. $2,598,705 2018-10-01 Operational 2021-06-30
Manitoba Little Grand Rapids Broadband Communications North inc. (BCN) Backbone network using satellite technology to enhance broadband capacity to 16 communities in the Northern region of Mantioba. $13,193,381 2019-08-01 Operational 2024-03-31
Manitoba Little Saskatchewan Broadband Communications North Inc. (BCN) Backbone network using fibre optic technology to enhance broadband capacity to 6 communities as well as a Last-mile network usingto reach underserved housholds in Northern Manitoba. $1,116,031 2019-04-01 Operational 2025-03-31
Manitoba Lowe Farm Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Manhattan Beach RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Margaret RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Mariapolis RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba McTavish Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 18 communities in the Pembina Valley region of South Central Manitoba. $6,930,080 2020-08-02 Operational 2022-06-30
Manitoba Medora RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Miami RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Nesbitt RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Neubergthal Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Neuenburg Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Neuhorst Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba New Bothwell Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 18 communities in the Pembina Valley region of South Central Manitoba. $6,930,080 2020-08-02 Operational 2022-06-30
Manitoba Ninette RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Norway House Kici Sipi Communications LP Backbone network using fibre optic technology to enhance broadband capacity to 2 communities in Northern Region of Manitoba. $19,967,992 2021-07-31 Detailed design & construction 2024-12-30
Manitoba Notre Dame de Lourdes RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Osterwick Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Otterburne Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 18 communities in the Pembina Valley region of South Central Manitoba. $6,930,080 2020-08-02 Operational 2022-06-30
Manitoba Oxford House (Bunibonibee Cree Nation) Broadband Communications North inc. (BCN) Backbone network using satellite technology to enhance broadband capacity to 16 communities in the Northern region of Mantioba. $13,193,381 2019-08-01 Operational 2024-03-31
Manitoba Pauingassi First Nation Bell Canada Backbone network using microwave to enhance broadband capacity to 8 communities in the province of Manitoba. $2,598,705 2018-10-01 Operational 2021-06-30
Manitoba Pauingassi First Nation Broadband Communications North inc. (BCN) Backbone network using satellite technology to enhance broadband capacity to 16 communities in the Northern region of Mantioba. $13,193,381 2019-08-01 Operational 2024-03-31
Manitoba Peguis Bell Canada Backbone network using microwave to enhance broadband capacity to 8 communities in the province of Manitoba. $2,598,705 2018-10-01 Operational 2021-06-30
Manitoba Pierson RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Pinaymootang First Nation Broadband Communications North Inc. (BCN) Backbone network using fibre optic technology to enhance broadband capacity to 6 communities as well as a Last-mile network usingto reach underserved housholds in Northern Manitoba. $1,116,031 2019-04-01 Planning 2025-03-31
Manitoba Poplar River (Poplar River First Nation) Broadband Communications North inc. (BCN) Backbone network using satellite technology to enhance broadband capacity to 16 communities in the Northern region of Mantioba. $13,193,381 2019-08-01 Operational 2024-03-31
Manitoba Pukatawagan (Mathias Colomb) Broadband Communications North inc. (BCN) Backbone network using satellite technology to enhance broadband capacity to 16 communities in the Northern region of Mantioba. $13,193,381 2019-08-01 Operational 2024-03-31
Manitoba Randolph Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 18 communities in the Pembina Valley region of South Central Manitoba. $6,930,080 2020-08-02 Operational 2022-06-30
Manitoba Rathwell RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Red Sucker Lake Broadband Communications North inc. (BCN) Backbone network using satellite technology to enhance broadband capacity to 16 communities in the Northern region of Mantioba. $13,193,381 2019-08-01 Operational 2024-03-31
Manitoba Reinfeld Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Reinland Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Riverside Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Roland Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Rosenfeld Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Rosengart Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Rosenort Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Rosetown Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Sanford Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 18 communities in the Pembina Valley region of South Central Manitoba. $6,930,080 2020-08-02 Operational 2022-06-30
Manitoba Schoenwiese Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Shamattawa First Nation Broadband Communications North inc. (BCN) Backbone network using satellite technology to enhance broadband capacity to 16 communities in the Northern region of Mantioba. $13,193,381 2019-08-01 Operational 2024-03-31
Manitoba Silver Plains Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 18 communities in the Pembina Valley region of South Central Manitoba. $6,930,080 2020-08-02 Operational 2022-06-30
Manitoba Somerset RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Sommerfeld Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba Sperling Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 18 communities in the Pembina Valley region of South Central Manitoba. $6,930,080 2020-08-02 Operational 2022-06-30
Manitoba St. Alphonse RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba St. Claude RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba St. Jean Baptiste Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba St. Joseph Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 29 communities in the region of Pembina Valley in Southern Manitoba. $10,253,862 2018-08-01 Operational 2021-03-31
Manitoba St. Leon RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba St. Malo Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 18 communities in the Pembina Valley region of South Central Manitoba. $6,930,080 2020-08-02 Operational 2022-06-30
Manitoba St. Martin Junction Broadband Communications North Inc. (BCN) Backbone network using fibre optic technology to enhance broadband capacity to 6 communities as well as a Last-mile network usingto reach underserved housholds in Northern Manitoba. $1,116,031 2019-04-01 Operational 2025-03-31
Manitoba St. Theresa Point Broadband Communications North inc. (BCN) Backbone network using satellite technology to enhance broadband capacity to 16 communities in the Northern region of Mantioba. $13,193,381 2019-08-01 Operational 2024-03-31
Manitoba Ste. Agathe Valley Fiber Limited Backbone network using fibre optic technology to enhance broadband capacity to 18 communities in the Pembina Valley region of South Central Manitoba. $6,930,080 2020-08-02 Operational 2022-06-30
Manitoba Stockton RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Swan Lake Reserve (Swan Lake) RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Tadoule Lake (Sayisi Dene First Nation) Broadband Communications North inc. (BCN) Backbone network using satellite technology to enhance broadband capacity to 16 communities in the Northern region of Mantioba. $13,193,381 2019-08-01 Operational 2024-03-31
Manitoba Treherne RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
Manitoba Vidir Bell Canada Backbone network using microwave to enhance broadband capacity to 8 communities in the province of Manitoba. $2,598,705 2018-10-01 Operational 2021-06-30
Manitoba Wasagamack (Wasagamack First Nation) Broadband Communications North inc. (BCN) Backbone network using satellite technology to enhance broadband capacity to 16 communities in the Northern region of Mantioba. $13,193,381 2019-08-01 Operational 2024-03-31
Manitoba Wawanesa RFNow Inc. Backbone network using fibre optic technology to enhance broadband capacity to 47 communities in the Central Plains region of South Central Manitoba. $9,239,058 2021-03-25 Operational 2024-03-31
New Brunswick Bains Corner Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
New Brunswick Bonny River Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
New Brunswick Davidson Lake Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
New Brunswick Fairfield Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
New Brunswick Jemseg Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
New Brunswick McDonald Corner Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
New Brunswick Parkindale Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
New Brunswick Rollingdam Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
New Brunswick South Branch Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
New Brunswick Southfield Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
New Brunswick Upham Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
New Brunswick Upper Hainesville Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Admirals Beach Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Aspen EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Aspey Brook EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Bacon Cove Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Baie Verte Bell Canada Backbone network using fibre optic technology to upgrade and provide resiliency broadband to 2 communities in the Baie Verte Peninsula region of Newfoundland & Labrador. $852,035 2018-11-01 Operational 2020-03-31
Newfoundland and Labrador Bear Cove Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 2 communities as well as a last-mile network to reach underserved housholds in the regions of Baie Verte and Connaigre Peninsulas, NL. $709,200 2018-10-01 Operational 2020-03-31
Newfoundland and Labrador Black Duck Cove EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Branch EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Britannia EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Burgoynes Cove EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Burgoynes Cove Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Burnside Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Cappahayden Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Capstan Island Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Cartwright Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Change Islands Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Channel-Port aux Basques Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 2 communities as well as a last-mile network to reach underserved housholds in the regions of Baie Verte and Connaigre Peninsulas, NL. $709,200 2018-10-01 Operational 2020-03-31
Newfoundland and Labrador Charlottetown Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Conche Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Cook's Harbour Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Cormack Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Cottrell's Cove Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Cow Head EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Croque Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 2 communities in the Northern Peninsula Region in the province of Newfoundland and Labrador. $349,883 2020-01-13 Operational 2021-03-31
Newfoundland and Labrador English Harbour East Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Fair Haven Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Fleur de Lys Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Forresters Point EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Forteau Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Fortune Harbour Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Fox Harbour Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Gallants Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Gaultois Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Georges Lake East EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Grand Le Pierre Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Grey River Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Harcourt Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Harricott EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Hatchet Cove EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Highlands EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Hopedale Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Island Harbour Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Jack Ladder Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Jackson's Arm Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Jamestown Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Kitchuses Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador L'Anse au Loup Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador L'Anse-au-Clair Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Laurenceton Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Little Harbour East Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Lodge Bay Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Long Beach EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Lower Lance Cove EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Makkovik Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Mary's Harbour Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador McCallum Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Miles Cove Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Ming's Bight Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Monroe Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Mud Lake Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Nain Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Natuashish Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador New Burnt Cove EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Newtown Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Norris Point Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 2 communities as well as a last-mile network to reach underserved housholds in the regions of Baie Verte and Connaigre Peninsulas, NL. $709,200 2018-10-01 Operational 2020-03-31
Newfoundland and Labrador O'Donnells Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Paul's Lake EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Petit Forte Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Petley EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Phillips Head EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Pidgeon Cove-St. Barbe EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Pinchgut Lake EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Pinware Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Point of Bay EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Pollards Point Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Port Albert Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Port Anson Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Port Hope Simpson Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Portland Creek EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Postville Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Ramea Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Red Bay Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Reidville Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 2 communities as well as a last-mile network to reach underserved housholds in the regions of Baie Verte and Connaigre Peninsulas, NL. $709,200 2018-10-01 Operational 2020-03-31
Newfoundland and Labrador Rencontre East Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Rigolet Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador River of Ponds EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Robinson Bight EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Rocky Harbour Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 2 communities as well as a last-mile network to reach underserved housholds in the regions of Baie Verte and Connaigre Peninsulas, NL. $709,200 2018-10-01 Operational 2020-03-31
Newfoundland and Labrador Seldom-Little Seldom Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Sheaves Cove EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Ship Harbour EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Snooks Harbour EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador Sop's Arm Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Southeast Bight Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador St. Alban's Bell Canada Backbone network using fibre optic technology to upgrade and provide resiliency broadband to 2 communities in the Baie Verte Peninsula region of Newfoundland & Labrador. $852,035 2018-11-01 Operational 2020-03-31
Newfoundland and Labrador St. Brendan's Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador St. Chads Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador St. Joseph's EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador St. Julien's Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 2 communities in the Northern Peninsula Region in the province of Newfoundland and Labrador. $349,883 2020-01-13 Operational 2021-03-31
Newfoundland and Labrador St. Lewis Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador St. Pauls EION Inc. Last-mile network using fixed wireless and mobile wireless technologies to reach underserved households in the northern peninsula and eastern region of Newfoundland. $2,209,835 2020-04-01 Operational 2021-12-22
Newfoundland and Labrador The Beaches Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador West St. Modeste Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Newfoundland and Labrador Winter Brook Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Northwest Territories Colville Lake (Behdzi Ahda First Nation) Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 8 communities in the Northwest Territories. $4,980,445 2021-04-01 Operational 2024-03-31
Northwest Territories Fort McPherson Government of Yukon Backbone network using fibre optic technology to enhance broadband resiliency to 4 communities in the Northwest Territories and Yukon. $30,000,000 2018-06-01 Detailed Design & Construction 2024-12-31
Northwest Territories Gameti First Nation Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 8 communities in the Northwest Territories. $4,980,445 2021-04-01 Operational 2024-03-31
Northwest Territories Inuvik (Inuvik Native) Government of Yukon Backbone network using fibre optic technology to enhance broadband resiliency to 4 communities in the Northwest Territories and Yukon. $30,000,000 2018-06-01 Detailed Design & Construction 2024-12-31
Northwest Territories Jean Marie River First Nation Northwestel Inc. Backbone network using fibre optic technology to enhance broadband capacity to the Jean Marie River First Nation in the Dehcho Region, NWT. $921,278 2019-05-01 Operational 2020-10-31
Northwest Territories Lutselk'e (Lutsel K'e Dene First Nation) Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 8 communities in the Northwest Territories. $4,980,445 2021-04-01 Operational 2024-03-31
Northwest Territories Paulatuk Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 8 communities in the Northwest Territories. $4,980,445 2021-04-01 Operational 2024-03-31
Northwest Territories Sachs Harbour Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 8 communities in the Northwest Territories. $4,980,445 2021-04-01 Operational 2024-03-31
Northwest Territories Trout Lake (Sambaa K'e First Nation) Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 8 communities in the Northwest Territories. $4,980,445 2021-04-01 Operational 2024-03-31
Northwest Territories Tsiigehtchic (Gwichya Gwich'in) Government of Yukon Backbone network using fibre optic technology to enhance broadband resiliency to 4 communities in the Northwest Territories and Yukon. $30,000,000 2018-06-01 Detailed Design & Construction 2024-12-31
Northwest Territories Ulukhaktok Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 8 communities in the Northwest Territories. $4,980,445 2021-04-01 Operational 2024-03-31
Northwest Territories Wekweètì (Dechi Laot'i First Nations) Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 8 communities in the Northwest Territories. $4,980,445 2021-04-01 Operational 2024-03-31
Nova Scotia Acadia TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Apple River Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Ashdale Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Bakers Settlement TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Bakers Settlement Eastlink Last-mile network using hybrid fibre coaxial technology to reach underserved households in the region of Lunenburg, Nova Scotia. $988,027 2018-10-22 Operational 2022-03-31
Nova Scotia Barss Corner TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Bayport Eastlink Backbone network using fibre optic technology to improve broadband capacity to 11 communities in Nova Scotia and Prince Edward Island. $1,649,454 2018-11-21 Operational 2022-03-31
Nova Scotia Bayswater Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Black Rock Municipality of the County of Kings Backbone network using fibre optic technology to enhance broadband capacity to 4 communities in the Annapolis Valley region of Nova Scotia. $2,509,788 2020-07-02 Operational 2022-09-30
Nova Scotia Blockhouse TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Blue Mountain Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Canada Creek Municipality of the County of Kings Backbone network using fibre optic technology to enhance broadband capacity to 4 communities in the Annapolis Valley region of Nova Scotia. $2,509,788 2020-07-02 Operational 2022-09-30
Nova Scotia Central Chebogue Eastlink Backbone network using fibre optic technology to improve broadband capacity to 11 communities in Nova Scotia and Prince Edward Island. $1,649,454 2018-11-21 Operational 2022-03-31
Nova Scotia Chelsea TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Cherry Hill TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Chester TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Chester Basin TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Chignecto Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Clementsvale Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Delaps Cove Municipality of the County of Annapolis Backbone network using fibre optic technology to enhance broadband capacity to 10 communities as well as last mile network using fibre optic technology to reach underserved households in the Annapolis Valley Region of Nova Scotia. $2,730,078 2020-05-04 Operational 2021-12-31
Nova Scotia Digby (North Range) Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Diligent River Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia East Dalhousie TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia East Ferry Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 2 communities in the southwestern region of Nova Scotia. $129,525 2020-04-20 Operational 2021-03-31
Nova Scotia East Walton Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Eden Lake Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Elmwood TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Falkland Ridge TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Feltzen South Eastlink Backbone network using fibre optic technology to improve broadband capacity to 11 communities in Nova Scotia and Prince Edward Island. $1,649,454 2018-11-21 Operational 2022-03-31
Nova Scotia Forties TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Fourchu Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Gavelton Eastlink Backbone network using fibre optic technology to improve broadband capacity to 11 communities in Nova Scotia and Prince Edward Island. $1,649,454 2018-11-21 Operational 2022-03-31
Nova Scotia Glooscap First Nation Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Gold River TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Greenfield Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Gunning Cove Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Halfway River Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Hemford TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Hemford Eastlink Last-mile network using hybrid fibre coaxial technology to reach underserved households in the region of Lunenburg, Nova Scotia. $988,027 2018-10-22 Operational 2022-03-31
Nova Scotia Hillsburn Municipality of the County of Annapolis Backbone network using fibre optic technology to enhance broadband capacity to 10 communities as well as last mile network using fibre optic technology to reach underserved households in the Annapolis Valley Region of Nova Scotia. $2,730,078 2020-05-04 Operational 2021-12-31
Nova Scotia Indian Point TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Ingomar Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Kingsburg Eastlink Backbone network using fibre optic technology to improve broadband capacity to 11 communities in Nova Scotia and Prince Edward Island. $1,649,454 2018-11-21 Operational 2022-03-31
Nova Scotia Kinsmans Corner Municipality of the County of Kings Backbone network using fibre optic technology to enhance broadband capacity to 4 communities in the Annapolis Valley region of Nova Scotia. $2,509,788 2020-07-02 Operational 2022-09-30
Nova Scotia Lawrencetown Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Lawrencetown Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Litchfield Municipality of the County of Annapolis Backbone network using fibre optic technology to enhance broadband capacity to 10 communities as well as last mile network using fibre optic technology to reach underserved households in the Annapolis Valley Region of Nova Scotia. $2,730,078 2020-05-04 Operational 2021-12-31
Nova Scotia Little River Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 2 communities in the southwestern region of Nova Scotia. $129,525 2020-04-20 Operational 2021-03-31
Nova Scotia Lochaber Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Maitland TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Maitland Bridge Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Margaretsville Municipality of the County of Annapolis Backbone network using fibre optic technology to enhance broadband capacity to 10 communities as well as last mile network using fibre optic technology to reach underserved households in the Annapolis Valley Region of Nova Scotia. $2,730,078 2020-05-04 Operational 2021-12-31
Nova Scotia Marriotts Cove TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Martins Point TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Martins River TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia McPhersons Mills Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Middlefield Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Midville Branch TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Minasville Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Mossman Corner TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia New Salem Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Newellton Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia North East Harbour Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia North Grand Pré Municipality of the County of Kings Backbone network using fibre optic technology to enhance broadband capacity to 4 communities in the Annapolis Valley region of Nova Scotia. $2,509,788 2020-07-02 Operational 2022-09-30
Nova Scotia North Lochaber Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia North River TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Northwest Cove Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Parkers Cove Municipality of the County of Annapolis Backbone network using fibre optic technology to enhance broadband capacity to 10 communities as well as last mile network using fibre optic technology to reach underserved households in the Annapolis Valley Region of Nova Scotia. $2,730,078 2020-05-04 Operational 2021-12-31
Nova Scotia Petite Rivière Eastlink Backbone network using fibre optic technology to improve broadband capacity to 11 communities in Nova Scotia and Prince Edward Island. $1,649,454 2018-11-21 Operational 2022-03-31
Nova Scotia Pinehurst TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Pleasant River TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Pleasant River Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Port Lorne Municipality of the County of Annapolis Backbone network using fibre optic technology to enhance broadband capacity to 10 communities as well as last mile network using fibre optic technology to reach underserved households in the Annapolis Valley Region of Nova Scotia. $2,730,078 2020-05-04 Operational 2021-12-31
Nova Scotia Port Royal Municipality of the County of Annapolis Backbone network using fibre optic technology to enhance broadband capacity to 10 communities as well as last mile network using fibre optic technology to reach underserved households in the Annapolis Valley Region of Nova Scotia. $2,730,078 2020-05-04 Operational 2021-12-31
Nova Scotia Port Wade Municipality of the County of Annapolis Backbone network using fibre optic technology to enhance broadband capacity to 10 communities as well as last mile network using fibre optic technology to reach underserved households in the Annapolis Valley Region of Nova Scotia. $2,730,078 2020-05-04 Operational 2021-12-31
Nova Scotia Prospect Eastlink Backbone network using fibre optic technology to improve broadband capacity to 11 communities in Nova Scotia and Prince Edward Island. $1,649,454 2018-11-21 Operational 2022-03-31
Nova Scotia Roseway Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Sandford Eastlink Backbone network using fibre optic technology to improve broadband capacity to 11 communities in Nova Scotia and Prince Edward Island. $1,649,454 2018-11-21 Operational 2022-03-31
Nova Scotia Scots Bay Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia South Side Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Springfield TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia St. Margaret Village Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Stoney Island Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Tancook Island TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia The Hawk Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Union Square TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Upper Blandford Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Victoria Beach Municipality of the County of Annapolis Backbone network using fibre optic technology to enhance broadband capacity to 10 communities as well as last mile network using fibre optic technology to reach underserved households in the Annapolis Valley Region of Nova Scotia. $2,730,078 2020-05-04 Operational 2021-12-31
Nova Scotia Virginia East Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Nova Scotia Western Shore TNC Wireless LTD Last-mile network using fixed wireless technology to reach underserved households in the region of Lunenburg and Queens Counties, Nova Scotia. $1,074,608 2018-09-10 Operational 2022-03-31
Nova Scotia Youngs Cove Municipality of the County of Annapolis Backbone network using fibre optic technology to enhance broadband capacity to 10 communities as well as last mile network using fibre optic technology to reach underserved households in the Annapolis Valley Region of Nova Scotia. $2,730,078 2020-05-04 Operational 2021-12-31
Nunavut Arctic Bay Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Arviat Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Baker Lake Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Cambridge Bay (Iqaluktuuttiaq) Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Cape Dorset Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Chesterfield Inlet Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Clyde River Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Coral Harbour Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Gjoa Haven Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Grise Fiord Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Hall Beach (Sanirajak) Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Igloolik Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Iqaluit Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Kimmirut Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Kugaaruk Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Kugluktuk Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Naujaat (Repulse Bay) Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Pangnirtung Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Pond Inlet Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Qikiqtarjuaq Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Rankin Inlet Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Resolute Bay Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Sanikiluaq Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Taloyoak Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Nunavut Whale Cove Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 25 communities in Nunavut. $49,900,000 2018-01-01 Operational 2021-03-31
Ontario Anishnaabeg of Naongashiing Bell Canada Backbone network to improve broadband capacity to 12 rural communities, in the regions of Northwest Ontario, Sault Ste. Marie-Algoma and Northeastern Ontario using fibre optic technology. $7,908,968 2019-01-01 Operational 2021-07-31
Ontario Apple Hill Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 9 communities in the United Counties of Prescotts and Russell, and the United Counties of Stormont, Dundas, Glengarry in Ontario. $7,512,835 2020-12-01 Detailed Design & Construction 2023-03-31
Ontario Attawapiskat The Western James Bay Telecom Network Backbone and last-mile network using fibre optic technology to improve broadband capacity to 3 communities in the region of southwestern James Bay, Ontario. $441,193 2018-09-14 Operational 2023-07-31
Ontario Batawa Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the Quinte region of Ontario. $10,779,826 2018-10-01 Detailed Design & Construction 2023-03-31
Ontario Beech Beach Bell Canada Backbone network to improve broadband capacity to 12 rural communities, in the regions of Northwest Ontario, Sault Ste. Marie-Algoma and Northeastern Ontario using fibre optic technology. $7,908,968 2019-01-01 Operational 2021-07-31
Ontario Berwick Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 9 communities in the United Counties of Prescotts and Russell, and the United Counties of Stormont, Dundas, Glengarry in Ontario. $7,512,835 2020-12-01 Detailed Design & Construction 2023-03-31
Ontario Bewdley Nexicom Inc. Backbone network using fibre optic technology to enhance broadband capacity to 5 communities in the Eastern Ontario. $2,948,219 2020-04-01 Operational 2023-03-31
Ontario Brunswick House Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 6 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the region of Northwestern Ontario. $3,468,772 2020-06-01 Operational 2024-12-31
Ontario Casselman Zoning Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 9 communities in the United Counties of Prescotts and Russell, and the United Counties of Stormont, Dundas, Glengarry in Ontario. $7,512,835 2020-12-01 Detailed Design & Construction 2023-03-31
Ontario Corbyville Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the Quinte region of Ontario. $10,779,826 2018-10-01 Detailed Design & Construction 2023-03-31
Ontario Dalkeith Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 9 communities in the United Counties of Prescotts and Russell, and the United Counties of Stormont, Dundas, Glengarry in Ontario. $7,512,835 2020-12-01 Detailed Design & Construction 2023-03-31
Ontario Deloro Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the Quinte region of Ontario. $10,779,826 2018-10-01 Detailed Design & Construction 2023-03-31
Ontario Dillon Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 6 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the region of Northwestern Ontario. $3,468,772 2020-06-01 Operational 2024-12-31
Ontario Dubreuilville Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 6 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the region of Northwestern Ontario. $3,468,772 2020-06-01 Operational 2024-12-31
Ontario Dunvegan Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 9 communities in the United Counties of Prescotts and Russell, and the United Counties of Stormont, Dundas, Glengarry in Ontario. $7,512,835 2020-12-01 Detailed Design & Construction 2023-03-31
Ontario Eldorado Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the Quinte region of Ontario. $10,779,826 2018-10-01 Detailed Design & Construction 2023-03-31
Ontario Elizabethville Nexicom Inc. Backbone network using fibre optic technology to enhance broadband capacity to 5 communities in the Eastern Ontario. $2,948,219 2020-04-01 Operational 2023-03-31
Ontario Fort Albany (Albany) The Western James Bay Telecom Network Backbone and last-mile network using fibre optic technology to improve broadband capacity to 3 communities in the region of southwestern James Bay, Ontario. $441,193 2018-09-14 Operational 2023-07-31
Ontario Fort Hope (Eabametoong First Nation) Rapid Lynx Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 5 communities as well as a Last-Mile network in the Matawa first Nation communities in the Ring of Fire region in Ontario. $37,100,000 2019-04-04 Detailed Design & Construction 2025-03-31
Ontario Fort Severn Keewaytinook Okimakanak Backbone network using satellite technology to enhance broadband capacity to 2 communities in the region of Northwestern Ontario. $5,629,990 2018-09-01 Operational 2019-03-31
Ontario Garden Hill Nexicom Inc. Backbone network using fibre optic technology to enhance broadband capacity to 5 communities in the Eastern Ontario. $2,948,219 2020-04-01 Operational 2023-03-31
Ontario Georgina Island (Chippewas of Georgina Island) The Regional Municipality of York Backbone network using fibre optic technology to enhance broadband capacity to 2 communities in the York region of Ontario. $2,000,000 2019-05-31 Operational 2021-03-31
Ontario Glasgow Station Cogeco Connexion Inc. Backbone network using fibre optic technology to enhance broadband capacity to 2 communities in eastern Ontario. $2,167,077 2020-01-31 Operational 2023-09-30
Ontario Glen Sandfield Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 9 communities in the United Counties of Prescotts and Russell, and the United Counties of Stormont, Dundas, Glengarry in Ontario. $7,512,835 2020-12-01 Detailed Design & Construction 2023-03-31
Ontario Greenfield Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 9 communities in the United Counties of Prescotts and Russell, and the United Counties of Stormont, Dundas, Glengarry in Ontario. $7,512,835 2020-12-01 Detailed Design & Construction 2023-03-31
Ontario Hilton Beach Bell Canada Backbone network to improve broadband capacity to 12 rural communities, in the regions of Northwest Ontario, Sault Ste. Marie-Algoma and Northeastern Ontario using fibre optic technology. $7,908,968 2019-01-01 Operational 2021-07-31
Ontario Inkerman Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 9 communities in the United Counties of Prescotts and Russell, and the United Counties of Stormont, Dundas, Glengarry in Ontario. $7,512,835 2020-12-01 Detailed Design & Construction 2023-03-31
Ontario Ivanhoe Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the Quinte region of Ontario. $10,779,826 2018-10-01 Detailed Design & Construction 2023-03-31
Ontario Kashechewan The Western James Bay Telecom Network Backbone and last-mile network using fibre optic technology to improve broadband capacity to 3 communities in the region of southwestern James Bay, Ontario. $441,193 2018-09-14 Operational 2023-07-31
Ontario Kejick (Iskatewizaagegan #39 Independent First Nation) Bell Canada Backbone network to improve broadband capacity to 12 rural communities, in the regions of Northwest Ontario, Sault Ste. Marie-Algoma and Northeastern Ontario using fibre optic technology. $7,908,968 2019-01-01 Operational 2021-07-31
Ontario Killbear Park Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 6 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the region of Northwestern Ontario. $3,468,772 2020-06-01 Operational 2024-12-31
Ontario Lonsdale Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the Quinte region of Ontario. $10,779,826 2018-10-01 Detailed Design & Construction 2023-03-31
Ontario Lovett Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the Quinte region of Ontario. $10,779,826 2018-10-01 Detailed Design & Construction 2023-03-31
Ontario Lunenburg Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 9 communities in the United Counties of Prescotts and Russell, and the United Counties of Stormont, Dundas, Glengarry in Ontario. $7,512,835 2020-12-01 Detailed Design & Construction 2023-03-31
Ontario Madsen Bell Canada Backbone network to improve broadband capacity to 12 rural communities, in the regions of Northwest Ontario, Sault Ste. Marie-Algoma and Northeastern Ontario using fibre optic technology. $7,908,968 2019-01-01 Operational 2021-07-31
Ontario Marlbank Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the Quinte region of Ontario. $10,779,826 2018-10-01 Detailed Design & Construction 2023-03-31
Ontario Marten Falls First Nation (Ogoki) Rapid Lynx Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 5 communities as well as a Last-Mile network in the Matawa first Nation communities in the Ring of Fire region in Ontario. $37,100,000 2019-04-04 Detailed Design & Construction 2025-03-31
Ontario Minahico Bell Canada Backbone network to improve broadband capacity to 12 rural communities, in the regions of Northwest Ontario, Sault Ste. Marie-Algoma and Northeastern Ontario using fibre optic technology. $7,908,968 2019-01-01 Operational 2021-07-31
Ontario Mishkeegogamang Keewaytinook Okimakanak (K-Net) Broadband project that will improve access to high-speed internet to 164 households located in 2 communities in Northern Ontario, using Fibre and Fixed Wireless. $304,107 2020-11-01 Operational 2023-03-31
Ontario Mishkeegogamang Keewaytinook Okimakanak (K-Net) Broadband project that will improve access to high-speed internet to 164 households located in 2 communities in Northern Ontario, using Fibre and Fixed Wireless. $304,107 2020-11-01 Operational 2023-03-31
Ontario Moose Deer Point Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 6 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the region of Northwestern Ontario. $3,468,772 2020-06-01 Detailed design & construction 2024-12-31
Ontario Mountain View Cogeco Connexion Inc. Backbone network using fibre optic technology to enhance broadband capacity to 2 communities in eastern Ontario. $2,167,077 2020-01-31 Operational 2023-09-30
Ontario Musky Bay Bell Canada Backbone network to improve broadband capacity to 12 rural communities, in the regions of Northwest Ontario, Sault Ste. Marie-Algoma and Northeastern Ontario using fibre optic technology. $7,908,968 2019-01-01 Operational 2021-07-31
Ontario Neskantaga First Nation Rapid Lynx Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 5 communities as well as a Last-Mile network in the Matawa first Nation communities in the Ring of Fire region in Ontario. $37,100,000 2019-04-04 Detailed Design & Construction 2025-03-31
Ontario New Osnaburgh Keewaytinook Okimakanak (K-Net) Broadband project that will improve access to high-speed internet to 164 households located in 2 communities in Northern Ontario, using Fibre and Fixed Wireless. $304,107 2020-11-01 Operational 2023-03-31
Ontario Nigigoonsiminikaaning First Nation Bell Canada Backbone network to improve broadband capacity to 12 rural communities, in the regions of Northwest Ontario, Sault Ste. Marie-Algoma and Northeastern Ontario using fibre optic technology. $7,908,968 2019-01-01 Operational 2021-07-31
Ontario Ojibway Nation of Saugeen Keewaytinook Okimakanak (K-Net) Broadband project that will improve access to high-speed internet to 164 households located in 2 communities in Northern Ontario, using Fibre and Fixed Wireless. $304,107 2020-11-01 Operational 2023-03-31
Ontario Parry Island (Wasauksing First Nation) Wasauksing First Nation Backbone network using fibre optic technology to enhance broadband capacity as well as Last-mile network using fibre optic technology to reach underserved households to the Wasauksing First Nation community in Ontario. $1,027,936 2018-11-01 Operational 2019-08-30
Ontario Peawanuck (Weenusk) Keewaytinook Okimakanak Backbone network using satellite technology to enhance broadband capacity to 2 communities in the region of Northwestern Ontario. $5,629,990 2018-09-01 Operational 2019-03-31
Ontario Queensborough Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the Quinte region of Ontario. $10,779,826 2018-10-01 Detailed Design & Construction 2023-03-31
Ontario Read Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the Quinte region of Ontario. $10,779,826 2018-10-01 Detailed Design & Construction 2023-03-31
Ontario Red Rock Bell Canada Backbone network to improve broadband capacity to 12 rural communities, in the regions of Northwest Ontario, Sault Ste. Marie-Algoma and Northeastern Ontario using fibre optic technology. $7,908,968 2019-01-01 Operational 2021-07-31
Ontario Roblin Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the Quinte region of Ontario. $10,779,826 2018-10-01 Detailed Design & Construction 2023-03-31
Ontario Sailors Encampment Bell Canada Backbone network to improve broadband capacity to 12 rural communities, in the regions of Northwest Ontario, Sault Ste. Marie-Algoma and Northeastern Ontario using fibre optic technology. $7,908,968 2019-01-01 Operational 2021-07-31
Ontario Sandhurst Shores Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the Quinte region of Ontario. $10,779,826 2018-10-01 Detailed Design & Construction 2023-03-31
Ontario Shannonville Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the Quinte region of Ontario. $10,779,826 2018-10-01 Detailed Design & Construction 2023-03-31
Ontario Snug Harbour Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 6 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the region of Northwestern Ontario $3,468,772 2020-06-01 Operational 2024-12-31
Ontario South Monaghan Nexicom Inc. Backbone network using fibre optic technology to enhance broadband capacity to 5 communities in the Eastern Ontario. $2,948,219 2020-04-01 Operational 2023-03-31
Ontario St. Charles Bell Canada Backbone network to improve broadband capacity to 12 rural communities, in the regions of Northwest Ontario, Sault Ste. Marie-Algoma and Northeastern Ontario using fibre optic technology. $7,908,968 2019-01-01 Operational 2021-07-31
Ontario Stockdale Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the Quinte region of Ontario. $10,779,826 2018-10-01 Detailed Design & Construction 2023-03-31
Ontario Strathcona Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the Quinte region of Ontario. $10,779,826 2018-10-01 Detailed Design & Construction 2023-03-31
Ontario Stratton Bell Canada Backbone network to improve broadband capacity to 12 rural communities, in the regions of Northwest Ontario, Sault Ste. Marie-Algoma and Northeastern Ontario using fibre optic technology. $7,908,968 2019-01-01 Operational 2021-07-31
Ontario Summer Beaver (Nibinamik First Nation) Rapid Lynx Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 5 communities as well as a Last-Mile network in the Matawa first Nation communities in the Ring of Fire region in Ontario. $37,100,000 2019-04-04 Detailed Design & Construction 2025-03-31
Ontario Thomasburg Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the Quinte region of Ontario. $10,779,826 2018-10-01 Detailed Design & Construction 2023-03-31
Ontario Twelve O'Clock Point Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the Quinte region of Ontario. $10,779,826 2018-10-01 Detailed Design & Construction 2023-03-31
Ontario Udora The Regional Municipality of York Backbone network using fibre optic technology to enhance broadband capacity to 2 communities in the York region of Ontario. $2,000,000 2019-05-31 Operational 2021-03-31
Ontario Wallbridge Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the Quinte region of Ontario. $10,779,826 2018-10-01 Detailed Design & Construction 2023-03-31
Ontario Warsaw Nexicom Inc. Backbone network using fibre optic technology to enhance broadband capacity to 5 communities in the Eastern Ontario. $2,948,219 2020-04-01 Operational 2023-03-31
Ontario Webequie Rapid Lynx Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 5 communities as well as a Last-Mile network in the Matawa first Nation communities in the Ring of Fire region in Ontario. $37,100,000 2019-04-04 Detailed Design & Construction 2025-03-31
Ontario Zion Hill Xplore Inc. Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the Quinte region of Ontario. $10,779,826 2018-10-01 Detailed Design & Construction 2023-03-31
Prince Edward Island Cap-Egmont Eastlink Backbone network using fibre optic technology to improve broadband capacity to 11 communities in Nova Scotia and Prince Edward Island. $1,649,454 2018-11-21 Operational 2022-03-31
Prince Edward Island Indian River Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Prince Edward Island Malpeque Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Prince Edward Island Spring Valley Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Prince Edward Island St. Chrysostome Eastlink Backbone network using fibre optic technology to improve broadband capacity to 11 communities in Nova Scotia and Prince Edward Island. $1,649,454 2018-11-21 Operational 2022-03-31
Prince Edward Island St-Raphaël Eastlink Backbone network using fibre optic technology to improve broadband capacity to 11 communities in Nova Scotia and Prince Edward Island. $1,649,454 2018-11-21 Operational 2022-03-31
Prince Edward Island Union Road Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 116 communities as well as a Last-Mile network using fibre optic technology to 2 additional communities to reach underserved households in the 4 provinces of Atlantic Canada. $27,241,450 2017-05-01 Operational 2021-08-30
Quebec Abercorn Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Adamsville Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Akulivik Tamaani Internet Backbone network using fibre optic and microwave technology to enhance broadband capacity to 5 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Nunavik region of Québec. $68,857,138 2018-04-01 Operational 2025-06-30
Quebec Albertville TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Alcove Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Armstrong TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Athelstan TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Aumond Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Aupaluk Tamaani Internet Backbone network using fibre optic and microwave technology to enhance broadband capacity to 5 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Nunavik region of Québec. $68,857,138 2018-04-01 Detailed Design & Construction 2025-06-30
Quebec Bacon's Bay Cogeco Connexion Inc. Backbone network using fibre optic technology to enhance broadband capacity to 4 communities as well as a Last-Mile networkto reach underserved households in the region of Estrie, QC. $743,604 2018-10-01 Operational 2022-09-30
Quebec Baie-des-Brises TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Baie-des-Sables TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Baie-Laperrière Cablevision Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the Abitibi-Témiscamingue region of Québec. $354,408 2018-07-01 Operational 2021-03-31
Quebec Baie-Saint-Ludger TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Baie-Trinité-Est TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Baldwin Mills TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Operational 2024-03-31
Quebec Barnston TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Operational 2024-03-31
Quebec Barrington TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Bassin DUCLOS & MICHAUD TÉLÉCOM INC. Backbone network using fibre optic technology to enhance broadband capacity to 5 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the region of Îles-de-la-Madeleine, QC. $1,061,482 2017-11-17 Operational 2022-09-30
Quebec Bécancour Municipalité Régionale de Comté (MRC) de Bécancour Last-Mile network using fibre optic technology to reach underserved households in some municipalities of the MRC de Bécancour in the Centre-du-Québec region, QC. $3,381,668 2017-11-17 Operational 2023-06-30
Quebec Bedford Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Black Cape TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Blackpool TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Blanc-Sablon TELUS Backbone network using micro-wave technology to enhance broadband capacity to 7 communities as well as a Last-Mile network using micro-wave technology to reach underserved households in the region of Basse-Côte-Nord, QC. $9,294,854 2018-11-01 Operational 2021-03-31
Quebec Bogton TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Bois-Franc Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Bolton Glen Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Bonaventure-Est TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Bondville Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Boudreau-Corners TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Operational 2024-03-31
Quebec Boulogne CoopTel Backbone network using fibre optic technology to enhance broadband capacity in 11 communities in the Montérégie and Estrie regions in central Québec. $554,000 2018-04-01 Operational 2021-03-31
Quebec Boynton TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Operational 2024-03-31
Quebec Brador TELUS Backbone network using micro-wave technology to enhance broadband capacity to 7 communities as well as a Last-Mile network using micro-wave technology to reach underserved households in the region of Basse-Côte-Nord, QC. $9,294,854 2018-11-01 Operational 2021-03-31
Quebec Bras-d'Apic TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Brébeuf TÉLÉ-CÂBLE LA CONCEPTION Last-mile network using fibre optic technology to enhance broadband capacity to underserved households in the Laurentians region, Québec. $630,828 2019-05-01 Operational 2022-03-31
Quebec Brigham Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Brill Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Broadlands TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Brome Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Bromont Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Brooklet TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Cacouna-Sud Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Calumet DÉRYtélécom Backbone network using fibre optic technology to provide resiliency broadband to 2 regions; Baie Verte and Connaigre Peninsulas, in the province of Newfoundland and Labrador. $294,392 2018-10-29 Operational 2021-03-31
Quebec Cantley 307NET Last-mile network using fibre optic technology to reach underserved households in the Cantley region of Québec. $2,126,417 2019-02-11 Operational 2023-09-30
Quebec Cap-au-Renard TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Cap-aux-Corbeaux Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Caps-de-Maria TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Cap-Seize TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Carillon DÉRYtélécom Backbone network using fibre optic technology to provide resiliency broadband to 2 regions; Baie Verte and Connaigre Peninsulas, in the province of Newfoundland and Labrador. $294,392 2018-10-29 Operational 2021-03-31
Quebec Cawood Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Chandler-Ouest TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Chapais Eeyou Communications Network Backbone network using optic fibre technology to provide broadband resiliency to 16 communities and Last-mile network using optic fibre technology to reach underserved households in 3 of these communities in the Nord-du-Québec and Mauricie regions in the province of Quebec. $4,970,180 2018-09-03 Operational 2023-06-30
Quebec Chapeau Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Chevery TELUS Backbone network using micro-wave technology to enhance broadband capacity to 7 communities as well as a Last-Mile network using micro-wave technology to reach underserved households in the region of Basse-Côte-Nord, QC. $9,294,854 2018-11-01 Operational 2021-03-31
Quebec Chichester Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Chute-Saint-Philippe Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Clapperton TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Clément Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Clemville TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Cloridorme TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Coaticook TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Operational 2024-03-31
Quebec Colombier TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Comins Mills TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Operational 2024-03-31
Quebec Compton TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Detailed Design & Construction 2024-03-31
Quebec Conseil des Atikamekw de Wemotaci Eeyou Communications Network Backbone network using optic fibre technology to provide broadband resiliency to 16 communities and Last-mile network using optic fibre technology to reach underserved households in 3 of these communities in the Nord-du-Québec and Mauricie regions in the province of Quebec. $4,970,180 2018-09-03 Operational 2023-06-30
Quebec Cookshire Transvision (Cookshire) inc. Backbone network using fibre optic technology to provide resiliency broadband to 2 communitie in the region of Estrie, QC. $262,800 2018-09-15 Detailed Design & Construction 2023-03-31
Quebec Couturier Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Cowansville Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Cushing DÉRYtélécom Backbone network using fibre optic technology to provide resiliency broadband to 2 regions; Baie Verte and Connaigre Peninsulas, in the province of Newfoundland and Labrador. $294,392 2018-10-29 Operational 2021-03-31
Quebec Dalesville MRC ARGENTEUIL Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the Laurentides region, QC. $4,652,355 2018-06-30 Operational 2023-09-30
Quebec Dalhousie Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Danby CoopTel Backbone network using fibre optic technology to enhance broadband capacity in 11 communities in the Montérégie and Estrie regions in central Québec. $554,000 2018-04-01 Operational 2021-03-31
Quebec Danford Lake Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Denison Mills Cogeco Connexion Inc. Backbone network using fibre optic technology to enhance broadband capacity to 4 communities as well as a Last-Mile networkto reach underserved households in the region of Estrie, QC. $743,604 2018-10-01 Operational 2022-09-30
Quebec Deschaillons-sur-Saint-Laurent Municipalité Régionale de Comté (MRC) de Bécancour Last-Mile network using fibre optic technology to reach underserved households in some municipalities of the MRC de Bécancour in the Centre-du-Québec region, QC. $3,381,668 2017-11-17 Operational 2023-06-30
Quebec Dewittville TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Dimock Creek (Micmacs of Gesgapegiag) TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Dixville TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Operational 2024-03-31
Quebec Domaine Enchanté TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Domaine-de-la-Paix CoopTel Backbone network using fibre optic technology to enhance broadband capacity in 11 communities in the Montérégie and Estrie regions in central Québec. $554,000 2018-04-01 Operational 2021-03-31
Quebec Domaine-des-Sapins MRC DE D'AUTRAY Backbone network using fibre optic technology to provide resiliency broadband as well as a Last-mile network using optic fibre technology to reach underserved households in the Municipalité Régionale de Comté de D'Autray in the Lanaudière region, QC. $2,278,633 2018-04-01 Operational 2022-03-31
Quebec Dorea TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Dufaultville TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Dundee TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Dune-du-Sud DUCLOS & MICHAUD TÉLÉCOM INC. Backbone network using fibre optic technology to enhance broadband capacity to 5 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the region of Îles-de-la-Madeleine, QC. $1,061,482 2017-11-17 Operational 2022-09-30
Quebec Dunham Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Earlstown TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Detailed Design & Construction 2024-03-31
Quebec East Farnham Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec East Hereford TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Operational 2024-03-31
Quebec Egan-Sud Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Estérel Cogeco Connexion Inc. Backbone network using fibre optic technology to enhance broadband capacity to 3 communities in the region of Saint-Luc-de-Vincennes. $78,029 2018-06-01 Operational 2021-03-31
Quebec Fairfax TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Operational 2024-03-31
Quebec Farnham Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Farnham Centre Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Fassett DÉRYtélécom Backbone network using fibre optic technology to provide resiliency broadband to 2 regions; Baie Verte and Connaigre Peninsulas, in the province of Newfoundland and Labrador. $294,392 2018-10-29 Operational 2021-03-31
Quebec Fatima Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the La Haute-Côte-Nord and Témiscouata regions of Québec. $604,261 2020-04-01 Operational 2022-07-31
Quebec Ferme-Neuve Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Festubert Solutions Ambra inc. Backbone network using fibre optic technology to enhance broadband capacity to 11 communities, as well as a Last-Mile network using microwave and wireless technology to 2 additional communities to reach underserved households in the regions of Mauricie and Lac St-Jean, QC. $15,281,955 2018-10-01 Operational 2023-09-30
Quebec Forestville TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Foster Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Franklin Centre TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Frelighsburg Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Fulford Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Gascons TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Gascons-Est TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Gascons-Ouest TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Gentilly Municipalité Régionale de Comté (MRC) de Bécancour Last-Mile network using fibre optic technology to reach underserved households in some municipalities of the MRC de Bécancour in the Centre-du-Québec region, QC. $3,381,668 2017-11-17 Operational 2023-06-30
Quebec Glen Almond Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Glen Sutton Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Glenelm TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Godbout TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Grace Park MRC ARGENTEUIL Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the Laurentides region, QC. $4,652,355 2018-06-30 Operational 2023-09-30
Quebec Grande-Cascapédia TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Grande-Vallée TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Grande-Vallée-des-Monts TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Grand-Pabos TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Grand-Remous Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Grenville DÉRYtélécom Backbone network using fibre optic technology to provide resiliency broadband to 2 regions; Baie Verte and Connaigre Peninsulas, in the province of Newfoundland and Labrador. $294,392 2018-10-29 Operational 2021-03-31
Quebec Gros-Morne TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Grosses-Roches TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Hallerton TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Harrington Harbour TELUS Backbone network using micro-wave technology to enhance broadband capacity to 7 communities as well as a Last-Mile network using micro-wave technology to reach underserved households in the region of Basse-Côte-Nord, QC. $9,294,854 2018-11-01 Operational 2021-03-31
Quebec Hatley Cogeco Connexion Inc. Backbone network using fibre optic technology to enhance broadband capacity to 4 communities as well as a Last-Mile networkto reach underserved households in the region of Estrie, QC. $743,604 2018-10-01 Operational 2022-09-30
Quebec Hatley Centre Cogeco Connexion Inc. Backbone network using fibre optic technology to enhance broadband capacity to 4 communities as well as a Last-Mile networkto reach underserved households in the region of Estrie, QC. $743,604 2018-10-01 Operational 2022-09-30
Quebec Havelock TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Havre-Aubert DUCLOS & MICHAUD TÉLÉCOM INC. Backbone network using fibre optic technology to enhance broadband capacity to 5 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the region of Îles-de-la-Madeleine, QC. $1,061,482 2017-11-17 Operational 2022-09-30
Quebec Henrysburg TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Herdman TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Hereford TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Operational 2024-03-31
Quebec Hervey-Jonction Solutions Ambra inc. Backbone network using fibre optic technology to enhance broadband capacity to 11 communities, as well as a Last-Mile network using microwave and wireless technology to 2 additional communities to reach underserved households in the regions of Mauricie and Lac St-Jean, QC. $15,281,955 2018-10-01 Operational 2023-09-30
Quebec Hervey-Jonction TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Hinchinbrooke TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Hollow Glen Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Honfleur TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Howick TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Innue Essipit Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the La Haute-Côte-Nord and Témiscouata regions of Québec. $604,261 2020-04-01 Operational 2022-07-31
Quebec Inukjuak Tamaani Internet Backbone network using fibre optic and microwave technology to enhance broadband capacity to 5 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Nunavik region of Québec. $68,857,138 2018-04-01 Operational 2025-06-30
Quebec Iron Hill Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Issoudun TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Ivujivik Tamaani Internet Backbone network using fibre optic and microwave technology to enhance broadband capacity to 5 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Nunavik region of Québec. $68,857,138 2018-04-01 Operational 2025-06-30
Quebec Jean-Noël Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Jogues Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Kangiqsualujjuaq Tamaani Internet Backbone network using fibre optic and microwave technology to enhance broadband capacity to 5 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Nunavik region of Québec. $68,857,138 2018-04-01 Detailed Design & Construction 2025-06-30
Quebec Kangiqsujuaq Tamaani Internet Backbone network using fibre optic and microwave technology to enhance broadband capacity to 5 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Nunavik region of Québec. $68,857,138 2018-04-01 Operational 2025-06-30
Quebec Kangirsuk Tamaani Internet Backbone network using fibre optic and microwave technology to enhance broadband capacity to 5 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Nunavik region of Québec. $68,857,138 2018-04-01 Detailed Design & Construction 2025-06-30
Quebec Kegaska TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Kegaska TELUS Backbone network using micro-wave technology to enhance broadband capacity to 7 communities as well as a Last-Mile network using micro-wave technology to reach underserved households in the region of Basse-Côte-Nord, QC. $9,294,854 2018-11-01 Operational 2021-03-31
Quebec Kelly TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Kensington TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Kiamika Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Kilmar MRC ARGENTEUIL Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the Laurentides region, QC. $4,652,355 2018-06-30 Operational 2023-09-30
Quebec Kingsbury CoopTel Backbone network using fibre optic technology to enhance broadband capacity in 11 communities in the Montérégie and Estrie regions in central Québec. $554,000 2018-04-01 Operational 2021-03-31
Quebec Kuujjuaq Tamaani Internet Backbone network using fibre optic and microwave technology to enhance broadband capacity to 5 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Nunavik region of Québec. $68,857,138 2018-04-01 Planning 2025-06-30
Quebec Kuujjuarapik Tamaani Internet Backbone network using fibre optic and microwave technology to enhance broadband capacity to 5 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Nunavik region of Québec. $68,857,138 2018-04-01 Operational 2025-06-30
Quebec La Bostonnais Solutions Ambra inc. Backbone network using fibre optic technology to enhance broadband capacity to 11 communities, as well as a Last-Mile network using microwave and wireless technology to 2 additional communities to reach underserved households in the regions of Mauricie and Lac St-Jean, QC. $15,281,955 2018-10-01 Operational 2023-09-30
Quebec La Conception TÉLÉ-CÂBLE LA CONCEPTION Last-mile network using fibre optic technology to enhance broadband capacity to underserved households in the Laurentians region, Québec. $630,828 2019-05-01 Operational 2022-03-31
Quebec La Croche Solutions Ambra inc. Backbone network using fibre optic technology to enhance broadband capacity to 11 communities, as well as a Last-Mile network using microwave and wireless technology to 2 additional communities to reach underserved households in the regions of Mauricie and Lac St-Jean, QC. $15,281,955 2018-10-01 Operational 2023-09-30
Quebec La Martre TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec La Minerve APTR Backbone and Last-mile network using fibre optic technology to improve broadband capacity in 3 communities and partially served households in the Laurentides region of Québec. $2,001,982 2018-06-01 Operational 2021-12-31
Quebec La Normandie TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec La Petite-France TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec La Rédemption TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec La Rivière TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec La Romaine (Montagnais de Unamen Shipu) TELUS Backbone network using micro-wave technology to enhance broadband capacity to 7 communities as well as a Last-Mile network using micro-wave technology to reach underserved households in the region of Basse-Côte-Nord, QC. $9,294,854 2018-11-01 Operational 2021-03-31
Quebec La Tabatière TELUS Backbone network using micro-wave technology to enhance broadband capacity to 7 communities as well as a Last-Mile network using micro-wave technology to reach underserved households in the region of Basse-Côte-Nord, QC. $9,294,854 2018-11-01 Operational 2021-03-31
Quebec La Trinité-des-Monts TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec La Tuque Solutions Ambra inc. Backbone network using fibre optic technology to enhance broadband capacity to 11 communities, as well as a Last-Mile network using microwave and wireless technology to 2 additional communities to reach underserved households in the regions of Mauricie and Lac St-Jean, QC. $15,281,955 2018-10-01 Operational 2023-09-30
Quebec L'Abattis Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Labelle APTR Backbone and Last-mile network using fibre optic technology to improve broadband capacity in 3 communities and partially served households in the Laurentides region of Québec. $2,001,982 2018-06-01 Operational 2021-12-31
Quebec Labelle TÉLÉ-CÂBLE LA CONCEPTION Last-mile network using fibre optic technology to enhance broadband capacity to underserved households in the Laurentians region, Québec. $630,828 2019-05-01 Operational 2022-03-31
Quebec Lac-à-Beauce Solutions Ambra inc. Backbone network using fibre optic technology to enhance broadband capacity to 11 communities, as well as a Last-Mile network using microwave and wireless technology to 2 additional communities to reach underserved households in the regions of Mauricie and Lac St-Jean, QC. $15,281,955 2018-10-01 Operational 2023-09-30
Quebec Lac-à-Foin Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Lac-Alain TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Lac-à-la-Truite Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 3 communities in the Southern region of Québec. $908,119 2020-09-01 Operational 2022-09-30
Quebec Lac-Blanc TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Lac-Bouchette Solutions Ambra inc. Backbone network using fibre optic technology to enhance broadband capacity to 11 communities, as well as a Last-Mile network using microwave and wireless technology to 2 additional communities to reach underserved households in the regions of Mauricie and Lac St-Jean, QC. $15,281,955 2018-10-01 Operational 2023-09-30
Quebec Lac-Brome Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Lac-Caroline MRC ARGENTEUIL Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the Laurentides region, QC. $4,652,355 2018-06-30 Operational 2023-09-30
Quebec Lac-Cayamant Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Lac-Chat Solutions Ambra inc. Backbone network using fibre optic technology to enhance broadband capacity to 11 communities, as well as a Last-Mile network using microwave and wireless technology to 2 additional communities to reach underserved households in the regions of Mauricie and Lac St-Jean, QC. $15,281,955 2018-10-01 Operational 2023-09-30
Quebec Lac-Deligny MRC DE D'AUTRAY Backbone network using fibre optic technology to provide resiliency broadband as well as a Last-mile network using optic fibre technology to reach underserved households in the Municipalité Régionale de Comté de D'Autray in the Lanaudière region, QC. $2,278,633 2018-04-01 Operational 2022-03-31
Quebec Lac-des-Écorces Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Lac-des-Seize-Îles Cogeco Connexion Inc. Backbone network using fibre optic technology to enhance broadband capacity to 3 communities in the region of Saint-Luc-de-Vincennes. $78,029 2018-06-01 Operational 2021-03-31
Quebec Lac-du-Milieu TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Lac-Édouard Solutions Ambra inc. Backbone network using fibre optic technology to enhance broadband capacity to 11 communities, as well as a Last-Mile network using microwave and wireless technology to 2 additional communities to reach underserved households in the regions of Mauricie and Lac St-Jean, QC. $15,281,955 2018-10-01 Operational 2023-09-30
Quebec Lac-Humqui TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Lac-Keatley MRC ARGENTEUIL Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the Laurentides region, QC. $4,652,355 2018-06-30 Operational 2023-09-30
Quebec Lac-Labelle APTR Backbone and Last-mile network using fibre optic technology to improve broadband capacity in 3 communities and partially served households in the Laurentides region of Québec. $2,001,982 2018-06-01 Operational 2021-12-31
Quebec Lac-Légaré Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the La Haute-Côte-Nord and Témiscouata regions of Québec. $604,261 2020-04-01 Operational 2022-07-31
Quebec Lac-MacDonald MRC ARGENTEUIL Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the Laurentides region, QC. $4,652,355 2018-06-30 Operational 2023-09-30
Quebec Lac-Pemichangan Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Lac-Saguay Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Lac-Saint-Paul Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Lac-Selby Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Lac-Trois-Saumons TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Lac-William Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Lakefield MRC ARGENTEUIL Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the Laurentides region, QC. $4,652,355 2018-06-30 Operational 2023-09-30
Quebec Lakeview MRC ARGENTEUIL Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the Laurentides region, QC. $4,652,355 2018-06-30 Operational 2023-09-30
Quebec L'Alverne TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec L'Annonciation Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Lanoraie MRC DE D'AUTRAY Backbone network using fibre optic technology to provide resiliency broadband as well as a Last-mile network using optic fibre technology to reach underserved households in the Municipalité Régionale de Comté de D'Autray in the Lanaudière region, QC. $2,278,633 2018-04-01 Operational 2022-03-31
Quebec L'Anse-à-la-Croix TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec L'Anse-Pleureuse TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec L'Anse-Saint-Jean Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Lascelles Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec L'Ascension Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Laval Municipalité Régionale de Comté (MRC) de Bécancour Last-Mile network using fibre optic technology to reach underserved households in some municipalities of the MRC de Bécancour in the Centre-du-Québec region, QC. $3,381,668 2017-11-17 Operational 2023-06-30
Quebec L'Avenir CoopTel Backbone network using fibre optic technology to enhance broadband capacity in 11 communities in the Montérégie and Estrie regions in central Québec. $554,000 2018-04-01 Operational 2021-03-31
Quebec Le Boom Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Le Petit-Saint-Marcellin TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Le Pré DUCLOS & MICHAUD TÉLÉCOM INC. Backbone network using fibre optic technology to enhance broadband capacity to 5 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the region of Îles-de-la-Madeleine, QC. $1,061,482 2017-11-17 Operational 2022-09-30
Quebec Le Précieux-Sang Municipalité Régionale de Comté (MRC) de Bécancour Last-Mile network using fibre optic technology to reach underserved households in some municipalities of the MRC de Bécancour in the Centre-du-Québec region, QC. $3,381,668 2017-11-17 Operational 2023-06-30
Quebec Lennoxville Transvision (Cookshire) inc. Backbone network using fibre optic technology to provide resiliency broadband to 2 communitie in the region of Estrie, QC. $262,800 2018-09-15 Detailed Design & Construction 2023-03-31
Quebec Les Buissons TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Les Côtes-du-Portage TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Les Escoumins Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the La Haute-Côte-Nord and Témiscouata regions of Québec. $604,261 2020-04-01 Operational 2022-07-31
Quebec Les Fonds TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Les Hauteurs-de-Rimouski TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Les Îlets-Jérémie TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Les Islets-Caribou TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Les Quarante TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec L'Immaculée-Conception TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Lost River MRC ARGENTEUIL Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the Laurentides region, QC. $4,652,355 2018-06-30 Operational 2023-09-30
Quebec Louisa MRC ARGENTEUIL Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the Laurentides region, QC. $4,652,355 2018-06-30 Operational 2023-09-30
Quebec Lourdes-de-Blanc-Sablon TELUS Backbone network using micro-wave technology to enhance broadband capacity to 7 communities as well as a Last-Mile network using micro-wave technology to reach underserved households in the region of Basse-Côte-Nord, QC. $9,294,854 2018-11-01 Operational 2021-03-31
Quebec Louvicourt Cablevision Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the Abitibi-Témiscamingue region of Québec. $354,408 2018-07-01 Operational 2021-03-31
Quebec Low Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Madeleine-Centre TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Magog CÂBLE AXION Backbone network using fibre optic technology to provide resiliency broadband to 3 communities in the region of Estrie, QC. $119,000 2018-07-01 Operational 2021-03-31
Quebec Maillard Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Manche-d'Épée TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Mandeville MRC DE D'AUTRAY Backbone network using fibre optic technology to provide resiliency broadband as well as a Last-mile network using optic fibre technology to reach underserved households in the Municipalité Régionale de Comté de D'Autray in the Lanaudière region, QC. $2,278,633 2018-04-01 Operational 2022-03-31
Quebec Mann TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Mann Settlement TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Mansonville CÂBLE AXION Backbone network using fibre optic technology to provide resiliency broadband to 3 communities in the region of Estrie, QC. $119,000 2018-07-01 Operational 2021-03-31
Quebec Maritana TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Marsoui TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Martin TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Martinville TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Detailed Design & Construction 2024-03-31
Quebec Massawippi Cogeco Connexion Inc. Backbone network using fibre optic technology to enhance broadband capacity to 4 communities as well as a Last-Mile networkto reach underserved households in the region of Estrie, QC. $743,604 2018-10-01 Operational 2022-09-30
Quebec Matagami Eeyou Communications Network Backbone network using optic fibre technology to provide broadband resiliency to 16 communities and Last-mile network using optic fibre technology to reach underserved households in 3 of these communities in the Nord-du-Québec and Mauricie regions in the province of Quebec. $4,970,180 2018-09-03 Operational 2023-06-30
Quebec Matane Société TELUS Communications Backbone and last-miles network using fibre technology, targetting 36 communities in the St. Lawrence River Region in the Province of Quebec. $7,500,000 2019-10-02 Planning 2024-03-31
Quebec Melboro CoopTel Backbone network using fibre optic technology to enhance broadband capacity in 11 communities in the Montérégie and Estrie regions in central Québec. $554,000 2018-04-01 Operational 2021-03-31
Quebec Middle Bay TELUS Backbone network using micro-wave technology to enhance broadband capacity to 7 communities as well as a Last-Mile network using micro-wave technology to reach underserved households in the region of Basse-Côte-Nord, QC. $9,294,854 2018-11-01 Operational 2021-03-31
Quebec Mille-Isles MRC ARGENTEUIL Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the Laurentides region, QC. $4,652,355 2018-06-30 Operational 2023-09-30
Quebec Moffet Cablevision Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the Abitibi-Témiscamingue region of Québec. $354,408 2018-07-01 Operational 2021-03-31
Quebec Mont-Cascades 307NET Last-mile network using fibre optic technology to reach underserved households in the Cantley region of Québec. $2,126,417 2019-02-11 Operational 2023-09-30
Quebec Montcerf-Lytton Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Mont-Laurier Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Mont-Saint-Michel Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Mont-Saint-Pierre Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Mont-Saint-Pierre TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Morigeau TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Murdochville TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Mutton Bay TELUS Backbone network using micro-wave technology to enhance broadband capacity to 7 communities as well as a Last-Mile network using micro-wave technology to reach underserved households in the region of Basse-Côte-Nord, QC. $9,294,854 2018-11-01 Operational 2021-03-31
Quebec Natashquan TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Nation Anishnabe du Lac Simon Cablevision Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the Abitibi-Témiscamingue region of Québec. $354,408 2018-07-01 Operational 2021-03-31
Quebec Neilon Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec New Carlisle West TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec New Richmond TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Newport Point TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Newport-Ouest TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Nominingue Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Notre-Dame-de-Pontmain Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Notre-Dame-de-Stanbridge Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Notre-Dame-du-Laus Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Notre-Dame-du-Rosaire TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Obaska Cablevision Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the Abitibi-Témiscamingue region of Québec. $354,408 2018-07-01 Operational 2021-03-31
Quebec Old-Harry DUCLOS & MICHAUD TÉLÉCOM INC. Backbone network using fibre optic technology to enhance broadband capacity to 5 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the region of Îles-de-la-Madeleine, QC. $1,061,482 2017-11-17 Operational 2022-09-30
Quebec Pabos Mills TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Padoue TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Pakuashipi (Montagnais de Pakua Shipi) TELUS Backbone network using micro-wave technology to enhance broadband capacity to 7 communities as well as a Last-Mile network using micro-wave technology to reach underserved households in the region of Basse-Côte-Nord, QC. $9,294,854 2018-11-01 Operational 2021-03-31
Quebec Papineauville DÉRYtélécom Backbone network using fibre optic technology to provide resiliency broadband to 2 regions; Baie Verte and Connaigre Peninsulas, in the province of Newfoundland and Labrador. $294,392 2018-10-29 Operational 2021-03-31
Quebec Parc-Davignon TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Parent Solutions Ambra inc. Backbone network using fibre optic technology to enhance broadband capacity to 11 communities, as well as a Last-Mile network using microwave and wireless technology to 2 additional communities to reach underserved households in the regions of Mauricie and Lac St-Jean, QC. $15,281,955 2018-10-01 Operational 2023-09-30
Quebec Paspébiac-Est TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Petite-Anse TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Petite-Vallée TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Petit-Poisson-Blanc Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Philipsburg Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Pied-du-Lac Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Pike River Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Pine Hill MRC ARGENTEUIL Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the Laurentides region, QC. $4,652,355 2018-06-30 Operational 2023-09-30
Quebec Pinguet TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Plage-Baie-Noire Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Plage-Somerville TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Pointe-à-Boisvert Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the La Haute-Côte-Nord and Témiscouata regions of Québec. $604,261 2020-04-01 Operational 2022-07-31
Quebec Pointe-à-la-Frégate TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Pointe-à-la-Garde TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Pointe-au-Chêne DÉRYtélécom Backbone network using fibre optic technology to provide resiliency broadband to 2 regions; Baie Verte and Connaigre Peninsulas, in the province of Newfoundland and Labrador. $294,392 2018-10-29 Operational 2021-03-31
Quebec Pointe-aux-Anglais TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Pointe-aux-Loups DUCLOS & MICHAUD TÉLÉCOM INC. Backbone network using fibre optic technology to enhance broadband capacity to 5 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the region of Îles-de-la-Madeleine, QC. $1,061,482 2017-11-17 Operational 2022-09-30
Quebec Pointe-aux-Outardes TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Pointe-Biron TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Pointe-Chambord Solutions Ambra inc. Backbone network using fibre optic technology to enhance broadband capacity to 11 communities, as well as a Last-Mile network using microwave and wireless technology to 2 additional communities to reach underserved households in the regions of Mauricie and Lac St-Jean, QC. $15,281,955 2018-10-01 Operational 2023-09-30
Quebec Pointe-des-Monts TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Pointe-Leggatt TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Port Lewis TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Portage-du-Cap DUCLOS & MICHAUD TÉLÉCOM INC. Backbone network using fibre optic technology to enhance broadband capacity to 5 communities as well as a Last-Mile network using fibre optic technology to reach underserved households in the region of Îles-de-la-Madeleine, QC. $1,061,482 2017-11-17 Operational 2022-09-30
Quebec Port-Daniel TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Port-Daniel-Centre TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Port-Daniel-Ouest TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Poste-des-Villeneuve Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Powerscourt TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Première nation de Whapmagoostui Tamaani Internet Backbone network using fibre optic and microwave technology to enhance broadband capacity to 5 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Nunavik region of Québec. $68,857,138 2018-04-01 Operational 2025-06-30
Quebec Première Nation des Innus de Nutashkuan TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Projet-Laplante TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Proulxville TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Puvirnituq Tamaani Internet Backbone network using fibre optic and microwave technology to enhance broadband capacity to 5 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Nunavik region of Québec. $68,857,138 2018-04-01 Operational 2025-06-30
Quebec Quaqtaq Tamaani Internet Backbone network using fibre optic and microwave technology to enhance broadband capacity to 5 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Nunavik region of Québec. $68,857,138 2018-04-01 Operational 2025-06-30
Quebec Querry TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Ragueneau TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Rapides-des-Joachims Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Rémigny Cablevision Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the Abitibi-Témiscamingue region of Québec. $354,408 2018-07-01 Operational 2021-03-31
Quebec Rimouski Société TELUS Communications Backbone and last-miles network using fibre technology, targetting 36 communities in the St. Lawrence River Region in the Province of Quebec. $7,500,000 2019-10-02 Planning 2024-03-31
Quebec Rivière-à-Claude TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Rivière-Bonaventure TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Rivière-Caplan TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Rivière-Lafleur Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Rivière-la-Madeleine TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Rivière-Matane TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Rivière-Matawin Solutions Ambra inc. Backbone network using fibre optic technology to enhance broadband capacity to 11 communities, as well as a Last-Mile network using microwave and wireless technology to 2 additional communities to reach underserved households in the regions of Mauricie and Lac St-Jean, QC. $15,281,955 2018-10-01 Operational 2023-09-30
Quebec Rivière-Port-Daniel TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Rivière-Sainte-Marguerite Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the La Haute-Côte-Nord and Témiscouata regions of Québec. $604,261 2020-04-01 Operational 2022-07-31
Quebec Rivière-Saint-Paul TELUS Backbone network using micro-wave technology to enhance broadband capacity to 7 communities as well as a Last-Mile network using micro-wave technology to reach underserved households in the region of Basse-Côte-Nord, QC. $9,294,854 2018-11-01 Operational 2021-03-31
Quebec Robidoux TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Robitaille TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Rockburn TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Roquemaure Cablevision Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the Abitibi-Témiscamingue region of Québec. $354,408 2018-07-01 Operational 2021-03-31
Quebec Rousseau TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Roxham TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Ruisseau-à-la-Loutre TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Ruisseau-à-Rebours TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Ruisseau-Castor TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Ruisseau-des-Olives TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Ruisseau-Gagnon TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Ruisseau-Leblanc TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Ruisseau-Vert TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Runnymede TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Russeltown Flats TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Sacré-Coeur Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 7 communities in the La Haute-Côte-Nord and Témiscouata regions of Québec. $604,261 2020-04-01 Operational 2022-07-31
Quebec Saint-Adalbert TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Adélard TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Adelme TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Aimé-du-Lac-des-Îles Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Saint-Alexandre-de-Kamouraska Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Saint-Alexandre-des-Lacs TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Alphonse-de-Caplan TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Ambroise Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Saint-André-de-Restigouche TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Anicet TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Saint-Antoine-Abbé TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Saint-Antoine-de-Tilly TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Armand Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Saint-Augustin TELUS Backbone network using micro-wave technology to enhance broadband capacity to 7 communities as well as a Last-Mile network using micro-wave technology to reach underserved households in the region of Basse-Côte-Nord, QC. $9,294,854 2018-11-01 Operational 2021-03-31
Quebec Saint-Barnabé-Nord Sogetel inc. Last-mile network using fibre optic technology to reach underserved households in the Mauricie region in Quebec. $21,361 2017-08-14 Operational 2018-10-12
Quebec Saint-Charles Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Saint-Charles-Garnier TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Claude Cogeco Connexion Inc. Backbone network using fibre optic technology to enhance broadband capacity to 4 communities as well as a Last-Mile networkto reach underserved households in the region of Estrie, QC. $743,604 2018-10-01 Operational 2022-09-30
Quebec Saint-Cléophas TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Cyr Cogeco Connexion Inc. Backbone network using fibre optic technology to enhance broadband capacity to 4 communities as well as a Last-Mile networkto reach underserved households in the region of Estrie, QC. $743,604 2018-10-01 Operational 2022-09-30
Quebec Saint-Cyrille-de-Wendover Cogeco Connexion Inc. Last-mile network using fibre optic technology to reach underserved households in the St-Joachim-de-Courval region in Quebec. $159,169 2018-03-01 Operational 2021-03-31
Quebec Saint-Damase TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Damase-des-Aulnaies TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-David-de-Falardeau Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Saint-Didace MRC DE D'AUTRAY Backbone network using fibre optic technology to provide resiliency broadband as well as a Last-mile network using optic fibre technology to reach underserved households in the Municipalité Régionale de Comté de D'Autray in the Lanaudière region, QC. $2,278,633 2018-04-01 Operational 2022-03-31
Quebec Sainte-Agathe-de-Lotbinière TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Sainte-Agnès-de-Dundee TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Sainte-Anne-du-Lac Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Sainte-Apolline TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Sainte-Barbe TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Sainte-Cécile-de-Lévrard Municipalité Régionale de Comté (MRC) de Bécancour Last-Mile network using fibre optic technology to reach underserved households in some municipalities of the MRC de Bécancour in the Centre-du-Québec region, QC. $3,381,668 2017-11-17 Operational 2023-06-30
Quebec Saint-Edgar TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Edmond MRC DE D'AUTRAY Backbone network using fibre optic technology to provide resiliency broadband as well as a Last-mile network using optic fibre technology to reach underserved households in the Municipalité Régionale de Comté de D'Autray in the Lanaudière region, QC. $2,278,633 2018-04-01 Operational 2022-03-31
Quebec Saint-Edmond-de-Grantham CoopTel Backbone network using fibre optic technology to enhance broadband capacity in 11 communities in the Montérégie and Estrie regions in central Québec. $554,000 2018-04-01 Operational 2021-03-31
Quebec Saint-Édouard CoopTel Backbone network using fibre optic technology to enhance broadband capacity in 11 communities in the Montérégie and Estrie regions in central Québec. $554,000 2018-04-01 Operational 2021-03-31
Quebec Sainte-Edwidge TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Detailed Design & Construction 2024-03-31
Quebec Sainte-Euphémie TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Sainte-Famille Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Sainte-Félicité TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Sainte-Félicité TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Sainte-Florence TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Sainte-Gertrude Municipalité Régionale de Comté (MRC) de Bécancour Last-Mile network using fibre optic technology to reach underserved households in some municipalities of the MRC de Bécancour in the Centre-du-Québec region, QC. $3,381,668 2017-11-17 Operational 2023-06-30
Quebec Sainte-Irène TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Sainte-Jeanne-d'Arc CoopTel Backbone network using fibre optic technology to enhance broadband capacity in 11 communities in the Montérégie and Estrie regions in central Québec. $554,000 2018-04-01 Operational 2021-03-31
Quebec Sainte-Jeanne-d'Arc TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Sainte-Louise TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Elzéar TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Elzéar TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Sainte-Marguerite-Marie TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Sainte-Paule TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Sainte-Rose-du-Nord Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Sainte-Sabine Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Saint-Étienne-de-Beauharnois TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Saint-Eugène-de-Grantham CoopTel Backbone network using fibre optic technology to enhance broadband capacity in 11 communities in the Montérégie and Estrie regions in central Québec. $554,000 2018-04-01 Operational 2021-03-31
Quebec Saint-Eugène-de-Ladrière TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Sainte-Véronique Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Saint-François Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Saint-François-de-Pabos TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Frédéric Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 3 communities in the Southern region of Québec. $908,119 2020-09-01 Operational 2022-09-30
Quebec Saint-Gabriel-de-Rimouski TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Georges TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Germain Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Saint-Godefroi TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Grégoire Municipalité Régionale de Comté (MRC) de Bécancour Last-Mile network using fibre optic technology to reach underserved households in some municipalities of the MRC de Bécancour in the Centre-du-Québec region, QC. $3,381,668 2017-11-17 Operational 2023-06-30
Quebec Saint-Herménégilde TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Detailed Design & Construction 2024-03-31
Quebec Saint-Honoré Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Saint-Ignace-de-Stanbridge Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Saint-Isidore-de-Gaspé TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Jacques-le-Majeur-de-Wolfestown Coopérative de télécommunication SJM Backbone network using fibre optic technology to enhance broadband capacity in the municipality of St-Jacques-le-Majeur in the Chaudière-Appalaches region, QC. $49,379 2019-04-01 Operational 2022-06-30
Quebec Saint-Jean-de-Cherbourg TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Jean-de-Matapédia TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Jean-sur-le-Lac Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Saint-Joachim-de-Courval Cogeco Connexion Inc. Last-mile network using fibre optic technology to reach underserved households in the St-Joachim-de-Courval region in Quebec. $159,169 2018-03-01 Operational 2021-03-31
Quebec Saint-Jogues TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Jogues-Sud TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Joseph-de-Mékinac Solutions Ambra inc. Backbone network using fibre optic technology to enhance broadband capacity to 11 communities, as well as a Last-Mile network using microwave and wireless technology to 2 additional communities to reach underserved households in the regions of Mauricie and Lac St-Jean, QC. $15,281,955 2018-10-01 Operational 2023-09-30
Quebec Saint-Laurent-de-l'île-d'Orléans Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Saint-Léandre TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Léonard-de-Portneuf TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Luc-de-Matane TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Luc-de-Vincennes Cogeco Connexion Inc. Backbone network using fibre optic technology to enhance broadband capacity to 3 communities in the region of Saint-Luc-de-Vincennes. $78,029 2018-06-01 Operational 2021-03-31
Quebec Saint-Malo TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Operational 2024-03-31
Quebec Saint-Marc-de-Latour TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Marcel TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Michel-de-Bellechasse TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Noël TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Octave-de-Métis TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Omer TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Pacôme Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Saint-Philémon-Sud TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Philippe DÉRYtélécom Backbone network using fibre optic technology to provide resiliency broadband to 2 regions; Baie Verte and Connaigre Peninsulas, in the province of Newfoundland and Labrador. $294,392 2018-10-29 Operational 2021-03-31
Quebec Saint-Philippe-de-Néri Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Saint-Pie-de-Guire Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 3 communities in the Southern region of Québec. $908,119 2020-09-01 Operational 2022-09-30
Quebec Saint-Pierre-de-l'Île-d'Orléans Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Saint-Pierre-les-Becquets Municipalité Régionale de Comté (MRC) de Bécancour Last-Mile network using fibre optic technology to reach underserved households in some municipalities of the MRC de Bécancour in the Centre-du-Québec region, QC. $3,381,668 2017-11-17 Operational 2023-06-30
Quebec Saint-Placide Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Saint-René TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-René-de-Matane TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Sébastien Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Saint-Séverin Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 3 communities in the Southern region of Québec. $908,119 2020-09-01 Operational 2022-09-30
Quebec Saint-Siméon-de-Bonaventure TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Simon-de-Rimouski TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Stanislas-de-Kostka TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Saint-Tharcisius TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Thomas-de-Caxton Sogetel inc. Last-mile network using fibre optic technology to reach underserved households in the Mauricie region in Quebec. $21,361 2017-08-14 Operational 2018-10-12
Quebec Saint-Tite Solutions Ambra inc. Backbone network using fibre optic technology to enhance broadband capacity to 11 communities, as well as a Last-Mile network using microwave and wireless technology to 2 additional communities to reach underserved households in the regions of Mauricie and Lac St-Jean, QC. $15,281,955 2018-10-01 Operational 2023-09-30
Quebec Saint-Tite-des-Caps Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Saint-Vianney TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Victor-de-Bonaventure TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Saint-Yvon TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Salaberry Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Sept-Îles Société TELUS Communications Backbone and last-miles network using fibre technology, targetting 36 communities in the St. Lawrence River Region in the Province of Quebec. $7,500,000 2019-10-02 Detailed Design & Construction 2024-03-31
Quebec Sheenboro Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Sherrington TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Shigawake TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Shigawake-Est TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Stanbridge East Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Stanbridge Station Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Stanhope TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Operational 2024-03-31
Quebec Ste-Anne-des-Monts Société TELUS Communications Backbone and last-miles network using fibre technology, targetting 36 communities in the St. Lawrence River Region in the Province of Quebec. $7,500,000 2019-10-02 Detailed Design & Construction 2024-03-31
Quebec Stonehame-et-Tewkesbury Coopérative de Câblodistribution de l'Arrière-Pays (CCAP) Last-mile network using fibre optic technology to reach underserved households in the municipality of Stoneham/Tewkesbury, Québec. $90,622 2020-04-01 Operational 2023-09-30
Quebec St-Venant-de-Paquette TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Operational 2024-03-31
Quebec Sutton Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Sutton Junction Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Tartigou TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Tasiujaq Tamaani Internet Backbone network using fibre optic and microwave technology to enhance broadband capacity to 5 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Nunavik region of Québec. $68,857,138 2018-04-01 Operational 2025-06-30
Quebec Tête-à-la-Baleine TELUS Backbone network using micro-wave technology to enhance broadband capacity to 7 communities as well as a Last-Mile network using micro-wave technology to reach underserved households in the region of Basse-Côte-Nord, QC. $9,294,854 2018-11-01 Operational 2021-03-31
Quebec The Crutch TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec The Fort TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Thivierge TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Tourville TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Ulchen TARGO Communications Inc Backbone network using fibre optic technology to enhance broadband capacity to 23 communities, as well as a Last-Mile network using fibre to the home technology to reach underserved households in the Montérégie region in the province of Québec. $2,399,424 2018-01-05 Operational 2023-12-31
Quebec Umiujaq Tamaani Internet Backbone network using fibre optic and microwave technology to enhance broadband capacity to 5 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Nunavik region of Québec. $68,857,138 2018-04-01 Operational 2025-06-30
Quebec Val-Barrette Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Valcartier-Village Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Val-d'Irène TELUS Backbone network using fibre optic technology to enhance broadband capacity to 141 communities in the regions of Gaspésie, Bas St-Laurent, Côte-Nord, Chaudière-Appalaches, Mauricie, Capitale-Nationale and Basse-Côte-Nord in the province of Québec. $12,111,784 2017-11-20 Operational 2022-03-31
Quebec Vieux-Fort TELUS Backbone network using micro-wave technology to enhance broadband capacity to 7 communities as well as a Last-Mile network using micro-wave technology to reach underserved households in the region of Basse-Côte-Nord, QC. $9,294,854 2018-11-01 Operational 2021-03-31
Quebec Village-de-la-Blague Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Villette TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Operational 2024-03-31
Quebec Wabassee Municipalité régionale de comté d'Antoine-Labelle Backbone network using fibre optic technology to provide resiliency broadband to 20 communities of the MRC d'Antoine-Labelle in the Laurentides region, QC. $958,962 2018-05-22 Operational 2022-09-30
Quebec Waltham Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Waterville TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Detailed Design & Construction 2024-03-31
Quebec Way's Mills TACTIC Backbone network using fibre optic technology to enhance broadband capacity to 8 communities as well as Last-mile network using fibre optic technology to reach underserved households of the MRC de Coaticook in the Estrie region, QC. $3,841,888 2019-02-26 Operational 2024-03-31
Quebec West Brome Internet Haut-Richelieu Backbone network using fibre optic technology to enchance broadband capacity to 9 communities as well as a last-mile network using fibre optic technology to reach underserved households in the Montérégie region of Québec. $8,115,780 2018-05-01 Operational 2023-09-30
Quebec Wheatland CoopTel Backbone network using fibre optic technology to enhance broadband capacity in 11 communities in the Montérégie and Estrie regions in central Québec. $554,000 2018-04-01 Operational 2021-03-31
Quebec Wilson's Corner Bell Canada Backbone network using fibre optic technology to enhance broadband capacity to 58 communities to reach underserved households in the regions of Saguenay-Lac-Saint-Jean, National Capital, Outaouais, Bas-Saint-Laurent, Chaudière-Appalaches, Laurentides, Montérégie and Central in the province of Québec. $7,001,866 2018-03-01 Operational 2022-06-30
Quebec Wilson's Corner 307NET Last-mile network using fibre optic technology to reach underserved households in the Cantley region of Québec. $2,126,417 2019-02-11 Operational 2023-09-30
Québec Aston-Jonction Sogetel Inc. Last-mile network using fixed fibre optic technology to reach underserved households in the MRC Nicolet-Yamaska of the Centre-du-Québec region, QC. $3,394,438 2019-04-01 Operational 2023-09-30
Québec Baie-du-Febvre Sogetel Inc. Last-mile network using fixed fibre optic technology to reach underserved households in the MRC Nicolet-Yamaska of the Centre-du-Québec region, QC. $3,394,438 2019-04-01 Operational 2023-09-30
Québec Belcourt Télébec Backbone network using fibre optic technology to enhance broadband capacity to 2 communities in the region of Northwestern Québec. $1,015,368 2020-10-01 Operational 2023-09-30
Québec Breault Sogetel Inc. Last-mile network using fixed fibre optic technology to reach underserved households in the MRC Nicolet-Yamaska of the Centre-du-Québec region, QC. $3,394,438 2019-04-01 Operational 2023-09-30
Québec La Visitation Sogetel Inc. Last-mile network using fixed fibre optic technology to reach underserved households in the MRC Nicolet-Yamaska of the Centre-du-Québec region, QC. $3,394,438 2019-04-01 Operational 2023-09-30
Québec Lac-Bolduc Groupe Maskatel LP Backbone network using fibre optic technology to enhance broadband capacity to 2 communities the Centre Region of Québec. $919,875 2020-10-01 Operational 2023-06-30
Québec Launay Télébec Backbone network using fibre optic technology to enhance broadband capacity to 2 communities in the region of Northwestern Québec. $1,015,368 2020-10-01 Operational 2023-09-30
Québec Nicolet Sogetel Inc. Last-mile network using fixed fibre optic technology to reach underserved households in the MRC Nicolet-Yamaska of the Centre-du-Québec region, QC. $3,394,438 2019-04-01 Operational 2023-09-30
Québec Notre-Dame-de-Pierreville Sogetel Inc. Last-mile network using fixed fibre optic technology to reach underserved households in the MRC Nicolet-Yamaska of the Centre-du-Québec region, QC. $3,394,438 2019-04-01 Operational 2023-09-30
Québec Pierreville Sogetel Inc. Last-mile network using fixed fibre optic technology to reach underserved households in the MRC Nicolet-Yamaska of the Centre-du-Québec region, QC. $3,394,438 2019-04-01 Operational 2023-09-30
Québec Saint-Célestin-Station Sogetel Inc. Last-mile network using fixed fibre optic technology to reach underserved households in the MRC Nicolet-Yamaska of the Centre-du-Québec region, QC. $3,394,438 2019-04-01 Operational 2023-09-30
Québec Sainte-Eulalie Sogetel Inc. Last-mile network using fixed fibre optic technology to reach underserved households in the MRC Nicolet-Yamaska of the Centre-du-Québec region, QC. $3,394,438 2019-04-01 Operational 2023-09-30
Québec Saint-Elphège Sogetel Inc. Last-mile network using fixed fibre optic technology to reach underserved households in the MRC Nicolet-Yamaska of the Centre-du-Québec region, QC. $3,394,438 2019-04-01 Operational 2023-09-30
Québec Sainte-Monique Sogetel Inc. Last-mile network using fixed fibre optic technology to reach underserved households in the MRC Nicolet-Yamaska of the Centre-du-Québec region, QC. $3,394,438 2019-04-01 Operational 2023-09-30
Québec Sainte-Perpétue Sogetel Inc. Last-mile network using fixed fibre optic technology to reach underserved households in the MRC Nicolet-Yamaska of the Centre-du-Québec region, QC. $3,394,438 2019-04-01 Operational 2023-09-30
Québec Saint-François-du-Lac Sogetel Inc. Last-mile network using fixed fibre optic technology to reach underserved households in the MRC Nicolet-Yamaska of the Centre-du-Québec region, QC. $3,394,438 2019-04-01 Operational 2023-09-30
Québec Saint-Léonard-d'Aston Sogetel Inc. Last-mile network using fixed fibre optic technology to reach underserved households in the MRC Nicolet-Yamaska of the Centre-du-Québec region, QC. $3,394,438 2019-04-01 Operational 2023-09-30
Québec Saint-Lucien Groupe Maskatel LP Backbone network using fibre optic technology to enhance broadband capacity to 2 communities the Centre Region of Québec. $919,875 2020-10-01 Operational 2023-06-30
Québec Saint-Wenceslas Sogetel Inc. Last-mile network using fixed fibre optic technology to reach underserved households in the MRC Nicolet-Yamaska of the Centre-du-Québec region, QC. $3,394,438 2019-04-01 Operational 2023-09-30
Québec Saint-Zéphirin Sogetel Inc. Last-mile network using fixed fibre optic technology to reach underserved households in the MRC Nicolet-Yamaska of the Centre-du-Québec region, QC. $3,394,438 2019-04-01 Operational 2023-09-30
Saskatchewan Abbey Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Admiral Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Amazon FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Arlington Beach FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Balone Beach FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 14 communities in the region of Saskatoon/Prince Albert, Saskatchewan. $5,939,449 2018-04-23 Operational 2021-03-31
Saskatchewan Berard Beach FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 14 communities in the region of Saskatoon/Prince Albert, Saskatchewan. $5,939,449 2018-04-23 Operational 2021-03-31
Saskatchewan Blumenheim FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 14 communities in the region of Saskatoon/Prince Albert, Saskatchewan. $5,939,449 2018-04-23 Operational 2021-03-31
Saskatchewan Blumenthal FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 14 communities in the region of Saskatoon/Prince Albert, Saskatchewan. $5,939,449 2018-04-23 Operational 2021-03-31
Saskatchewan Bradwell FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Brock Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Burstall Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Cabri Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Cadillac Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Climax Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Colesdale Park FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Consul Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Crystal Springs FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 14 communities in the region of Saskatoon/Prince Albert, Saskatchewan. $5,939,449 2018-04-23 Operational 2021-03-31
Saskatchewan Denzil Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Domremy Beach FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 14 communities in the region of Saskatoon/Prince Albert, Saskatchewan. $5,939,449 2018-04-23 Operational 2021-03-31
Saskatchewan Eastend Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Eston Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Etters Beach FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Fox Valley Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Glen Harbour FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Greenfeld FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 14 communities in the region of Saskatoon/Prince Albert, Saskatchewan. $5,939,449 2018-04-23 Operational 2021-03-31
Saskatchewan Gruenthal FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 14 communities in the region of Saskatoon/Prince Albert, Saskatchewan. $5,939,449 2018-04-23 Operational 2021-03-31
Saskatchewan Hagen FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 14 communities in the region of Saskatoon/Prince Albert, Saskatchewan. $5,939,449 2018-04-23 Operational 2021-03-31
Saskatchewan Imperial Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Island View FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Kannata Valley FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Kelvington Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Kipling Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Kyle Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Leader Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Maple Creek Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Milestone Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Mohr's Beach FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Netherhill Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Neuhorst FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 14 communities in the region of Saskatoon/Prince Albert, Saskatchewan. $5,939,449 2018-04-23 Operational 2021-03-31
Saskatchewan Nikorick Beach FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 14 communities in the region of Saskatoon/Prince Albert, Saskatchewan. $5,939,449 2018-04-23 Operational 2021-03-31
Saskatchewan North Colesdale Park FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Pelican Pointe FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Ponteix Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Renown FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Richmound Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Riversedge FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 14 communities in the region of Saskatoon/Prince Albert, Saskatchewan. $5,939,449 2018-04-23 Operational 2021-03-31
Saskatchewan Shaunavon Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Shields FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Simpson FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Sorenson's Beach FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Southey Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Spring Bay FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Thode FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Tway FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 14 communities in the region of Saskatoon/Prince Albert, Saskatchewan. $5,939,449 2018-04-23 Operational 2021-03-31
Saskatchewan Uhl's Bay FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Venn FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Vibank Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Wakaw Lake FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 14 communities in the region of Saskatoon/Prince Albert, Saskatchewan. $5,939,449 2018-04-23 Operational 2021-03-31
Saskatchewan Waterpark Estates FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Saskatchewan Watrous Saskatchewan Telecommunications Backbone network using fibre optic technology to enhance broadband capacity to 27 communities in the Southern region of Saskatchewan. $5,337,573 2018-05-01 Operational 2022-11-17
Saskatchewan Zelma FlexNetworks Backbone network using fibre optic technology to enhance broadband capacity to 21 communities in the South Central region of Saskatchewan. $10,159,371 2019-07-02 Operational 2022-03-31
Yukon Dawson (Tr'ondëk Hwëch'in) Government of Yukon Backbone network using fibre optic technology to enhance broadband resiliency to 4 communities in the Northwest Territories and Yukon. $30,000,000 2018-06-01 Detailed Design & Construction 2024-12-31
Yukon Old Crow (Vuntut Gwitchin First Nation) Northwestel Inc. Backbone network using satellite technology to enhance broadband capacity to 8 communities in the Northwest Territories. $4,980,445 2021-04-01 Operational 2024-03-31